| |
Regional Power Supply Adequacy/Reliability Study
Status Report and Report on the Third Advisory Committee Meeting
February 18, 1999
The Advisory Committee held its third meeting on Thursday, February 18 in the
Council's Offices in Portland. Committee members attending were: Ray Bliven,
representing some aluminum companies; Steve Kerns, BPA; Ed Clarke, Ida-West; Tim
Smith, BPA; Linc Wolverton, Industrial Customers of NW Utilities; Rich Lauckhart,
NW Power Enterprises; Jack Williams, Oregon PUC; Steve Knudsen, PG&E Gas
Transmission; Chris Elliot, Northwest Power Pool; Marty Howard, representing the
Columbia River Inter-Tribal Fish Commission. Also in attendance were Carl
VanHoff, Supply System; David Stewart-Smith, Oregon Office of Energy; Kurt
Granat, PacifiCorp; Mike McCoy, Consultant.
Status of the modeling effort
The objective of the modeling effort is to be able to describe in
probabilistic terms the magnitudes and frequencies of unserved load. Because we
no longer can assume that if we have adequate energy over a period we will be
able to cover peak loads with the hydro system, the analysis will go down to the
hourly level as well as the more usual monthly analysis. Pete Swartz began with
a discussion of the status of the modeling effort (GENESYS). He discussed his
"punch list" for the key items remaining. The punch list includes:
- Implementing inclusion of non-treaty storage
- Including the most up-to-date firm export and import contracts data
- Incorporating stochastic variation of hydro capacity at a given energy
- Revised hydro Forced Outage Rates and updated capacity curves from
Trapezoidal method.
- Improve thermal forced outage treatment
- Refine data assumptions (reference load, resources, transfer
capabilities, Banks Lake)
- Integrate multi-dam hydro regulator
- Refine hydro pricing
- Reserves accounting
- Incorporating the ability to address changes in system configuration
during the study
Pete then turned it over to John Fazio who described some of the work to
model the hydro blocks in GENESYS. His presentation is attached.
The key point of his presentation was that there is a relatively large block of
hydro below contractual drafting rights that is not normally used because of
fish and wildlife constraints. It may be possible to temporarily violate those
constraints without adversely affecting flow requirements for fish later in the
year. It will cost something to purchase energy to permit the reservoirs to
refill after the constraints have been violated for reliability, but that cost
could be considerably less than the cost of either curtailment or alternative
means of maintaining reliability. Use of this block of hydro would be
controversial. There was some discussion of whether use of this water should
even be considered in this analysis. On the other hand, if infrequent use of a
portion of that hydro block can improve reliability without adversely affecting
fish flow requirements, it would seem to be a reasonable option. Staff
subsequently decided to analyze the reliability situation without use of that
hydro block and then, if necessary, evaluate the effect of using a portion of
that block on the frequency and the magnitudes by which fish flow targets are
not met.
Pete returned to describe the model structure and the underlying approach to
modeling the hydro dispatch. The representation of the power system incorporated
in the model is shown on Figure 1.

Figure 1
The power system is represented by 5 areas corresponding to the Pacific
Northwest -- East (of the Cascades), the Pacific Northwest -- West, Northern
California, Southern California and the Desert Southwest, and Canada. The
transmission links between them are represented with transfer capabilities. The
South to North Transfer capabilities vary as a function of net loads west of the
Cascades (PNW West) consistent with Bonneville transmission nomograms. A
dispatch of generation to meet load is performed for the PNW resources.
Resources in the other areas are treated as a supply curve in an amount
sufficient to fill the transmission links if necessary. Conservatively it has
been assumed there is no import capability from Canada. The model will import
from California when it is economic to do so. The focus of this study has been
winter time reliability. In those months, California and the desert Southwest
typically have significant excess generation capability. Consequently, it has
not been felt that a more sophisticated representation was necessary. Comment
was made that August can be a problem as well. A more complete representation
can be incorporated if necessary.
Pete then gave a real time demonstration of the operation of the model. It
was emphasized that THE RESULTS ARE ILLUSTRATIVE ONLY. The model simulated a
series of Decembers, Januarys and Februarys, 2002 -- 2005 assuming very poor
water (1937) and extreme weather conditions. The analysis assumed 1000 MW of new
gas fired CCCTs in the Northwest and, as noted earlier, treatment of reserve
requirements has not yet been incorporated. As would be expected, the model
demonstrates periods with significant unserved loads under these conditions.
Assumptions about the ability to rely on imports have the ability to
significantly affect the results. The results of a several hundred game
simulation in which water and weather conditions were allowed to vary
stochastically were also examined. These illustrated the nature of problem --
the possibility of significant unserved load but with low probability of
occurance.
There was discussion about the assumptions underlying the analysis. The fact
that reserve requirements were not being treated adequately in the model was
acknowledged. As noted earlier, treatment of reserves is on the "punch
list". Similarly, it is understood that use of the lower blocks of hydro is
by no means a foregone conclusion. It may prove that it is not possible to use
those blocks.
The more difficult question is the treatment of imports and exports. The
logic in the model says that if the Northwest is experiencing tight supplies
and, hence, high prices AND there is power available outside of the region at a
lower cost (including losses and transmission charges), that power will find its
way into the region up to the limits of the transmission transfer capability.
Similarly, if firm export commitments of NW utilities can be offset by purchases
in the importing region (frequently referred to as counter-scheduling)at a cost
less than the value of power in the Northwest, they will be.
Some members of the committee felt that those were not necessarily good
assumptions. Concerns were raised at an earlier meeting regarding
counter-scheduling. The concern was that unless firm transmission could be
obtained to deliver the purchases made in the importing region, the purchaser
might not allow its contract to be fulfilled through counter scheduling. They
also cited the experience in last year's December cold snap in which there
were few imports. California also experienced colder than normal weather and
some gas fired generation was out of service because it did not have firm gas
transmission rights. As a consequence, California prices were also high at a
time when prices were high in the Northwest. This doesn't necessarily
invalidate the logic in the model, but it does suggest that there can be
circumstances in which power which would ordinarily be available for purchase
from the Southwest might not be available. Staff will review what was going on
during the December event to see what, if anything, it tells us with respect to
the underlying logic of the modeling.
The point was made fairly emphatically that since the Bonneville
Administrator is on record raising concerns about the large magnitude of
regional deficits, we had better have a very good explanation if we come up with
any different results. We should be able to duplicate the magnitude of the
monthly and annual energy deficits from Bonneville's White Book if we make
consistent assumptions about loads, new resource development, exports and
imports.
Natural Gas
Steve Knudsen of PG&E Gas Transmission made some observations regarding
gas price and supply. He noted that the gas prices we are using are reasonable
for now. However, they may understate future prices. The primary reason is that
our current price estimates assume that developers will not purchase firm
pipeline capacity for all of their requirements, relying instead on cheaper,
non-firm released capacity for some. Steve suggested that as the pipeline
capacity market tightens, that may no longer be a good assumption and would push
the transportation component of the gas price up. He also noted that during the
December cold snap, several Northern California power plants were unable to run
because they did not have firm pipeline capacity. He said he was unaware of any
near term plans for expansion of gas pipeline capacity. However, "if you
come, they will build it."
What Are We Doing this For?
The discussion then turned to the question raised by a short paper submitted
by committee member Carol Opatrny (attached). Lon
Peters submitted a memo in support of Carol's argument (attached).
Unfortunately, neither Carol nor Lon were present to represent their views in
person. At the almost certain risk of misrepresentation, Carol's thesis was
described as follows:
This study of regional supply adequacy is premised on the assumption that
the restructuring of the electricity industry with the potential for retail
competition, even though only partial, has created uncertainty about where
the responsibility to assure an adequate power supply resides. Carol argues
that retail access is far from a certainty, with only one state in the
Northwest having moved that direction. Without retail access, the serving
utility's obligation to serve is intact and is, for that matter, a matter
of state law in both Oregon and Washington (and probably Idaho as well).
Even if there is retail access, the local utility, absent any change in
state laws, retains this responsibility and is in a position assure
adequacy. It can accomplish this either acting on its own, if it operates
its own control area, or through its control area operator. Further, there
are no impediments to the utility seeking and implementing the least cost
combination of supply and demand side options to assure reliability.
Finally, there is no need for additional analysis to better define the
problem nor is there any need for action at the regional level to address
what is essentially a local responsibility.
Dick Watson attempted to clarify to objectives of the project. He indicated
that the Council would continue with the modeling effort because these are
improvements to the Council's analytic tools that we would want to make in any
event. However, the richer understanding of the situation that the modeling can
provide will, we think, be helpful in thinking about the policy issues.
With respect to the policy issues, the Council has never had any intent of
making policy for reliability. Its intent was to provide information that would
be useful to those who will be making decisions that can affect the adequacy and
reliability of the region's power supply. To accomplish, we are not trying to
predict where restructuring will come out. The intent is to try to carry out a
fairly disciplined exploration of the options for assuring adequate supply and
the pros and cons associated with each, probably as a function of position on
the spectrum from regulated monopolies to retail open access. Carol has
postulated one option -- maintaining the obligation to serve at the local level.
There are others that probably should also be evaluated. If, for example, the
region pursues the formation of an Independent (Transmission) System Operator
(ISO), should the ISO have the responsibility for assuring adequate supply as is
the case with the California ISO?
Linc Wolverton stated that he believed that restructuring was proceeding
further than Carol seemed to assume and that it was not altogether clear that
the local distribution utility was best equipped to address the adequacy issue.
Others indicated that despite indications of potential deficit, no one was
building anything.
Linc went on to suggest that the choices boiled down to insurance or the
market. Insurance involves determining who has the responsibility and the
ability to pay for keeping the "cats and dogs" (older, inefficient
plants) around in order to assure adequate supply for infrequent adverse
situations.
Regarding the question of the value of additional analysis, both the
representatives of the developer community and the regulators indicated they
felt that there was need for better information to help decision-making. The
fact that analysis shows a large problem in the event of no new resource
development, adverse hydro conditions and severe weather is attention-getting
but not that useful.
The group decided to continue this discussion when Carol and others who
shared her views could be present. In the meantime, work should proceed on the
analytics to define whether or not and to what extent we really have a problem.
Resource Assumptions
The afternoon concluded with a presentation by Jeff King. Jeff presented data
on plant availability; the availability of out-of-region resources that
heretofore have been dedicated to Northwest loads (e.g., Colstrip); assumptions
regarding the characteristics (heat rates, capital and fixed and variable
O&M costs, permitting and construction periods); fuel prices and financing
assumptions for new resources that could be developed in the Northwest. His
presentation is attached. Comments were
primarily directed to the issue raised earlier. To what extent can we expect the
owners of plants with contractual obligations outside the Northwest to sell the
output to the Northwest and satisfy their contractual obligation with purchases
made in the Southwest when relative prices and availability of supply make it
attractive to do so.
Next Meeting
The next meeting was set for Wednesday, March 31, 9AM to Noon at the Council's
offices.
^ top
|
|