| |
Adequacy/Reliability Study Proposed Analytical (Phase 1) Work Plan
December 4, 1998
Note: This work plan will be revised as necessary as the project
project proceeds:
What questions are we addressing in the overall study?
- What is the level of reliability, in probabilistic terms, that we
would expect in the future assuming no new generation supply, no new
transmission and no new demand-side response? Ability to
meet load on an hourly basis, i.e., both energy and capacity, is at
issue.
- What is the level of reliability, in probabilistic terms, that we
would expect to get from market-driven generation suppliers?
- What are the current institutional constraints on the generation
supply market, if any (lack of market information, lack of purchasers
with load responsibility, etc.)? Are they significant enough to
be concerned about?
- What are the current institutional constraints on demand response to
market conditions? (In this case we can start by assuming
they are currently significant.)
- What actions could be taken to make the market more efficient,
both for supply entrants and demand-side entrants?
- What actions are likely to lead to a dead end and should be avoided?
The technical analysis described in this workplan is intended to answer
the first two questions and set the background for the policy analysis of
the remaining three.
Note that there will be locational advantages to generation and/or
demand reductions in some areas (generation deficient areas with impending
transmission constraints like the west side, south of the north-of-John
Day cut plane to replace potential fish loss of generation supporting
intertie capability). Bonneville has raised at NRTA an transmission
issue that is parallel to ours on the generation side: what transmission
improvements are needed to maintain future reliability and who will pay
for them. In certain areas, generation and transmission are
substitutes for each other and the two studies will need to be considered
together. The modeling for the Council's study will represent some
transmission constraints within the Northwest, and their effects, in a
simplified manner.
Analytical Process
The key analytical problem is doing a frequency analysis on a hourly
basis for unserved load under water, load, and resource availability
uncertainty. The ideal would be to end with a duration curve of
unserved load with existing resources: The peak would be load not
served under the adopted reliability criterion and the remaining layer
would be load we would expect to be met by new resources, however they
would be developed (Part 2 of the project ? institutional and policy
analysis). The reliability criterion is a potential variable in
this.
The random variables are water, extreme temperature events and thermal
forced outages.
The following sections describe pieces of the analytical process.
The expanded model described below is in need of a new name. ?ISAAC?
is used below, recognizing its lineage. Suggestions are welcome and
may be rewarded.
Weather-driven demand input into ISAAC
- Monthly and hourly load shapes from hourly load model, using
regional temperature data as input.
- We are interested in random variation in hourly load shapes within
ISAAC to account for weather effects, which would replace secular
trend uncertainty which we take as fixed for this study.
- Issue: degree of correlation of temperatures (and loads) with water
conditions
- Proposed mechanism: Pursue availability of regional hourly
temperature data, weight according to ELCAP site weights (this
structure built into ISAAC and the load model already), attach to
historical hydro data and make random draws from the combined
set. Each draw of a year would give both a hydro record and an
hourly temperature record that occurred that year.
- To investigate: Whether cold spells, the real area of concern, are
correlated with winter average temperatures. If they are not, an
additional random variable would be needed; if they are, the above
procedure should capture it properly.
- For scenario analysis, specific load shapes and levels can be used
as well.
Import capability
Import capability on the southern intertie is a function of net west
side load and east-to-west flows on the Midpoint-Summer Lake line.
The winter 1998-99 operating limits based on analysis of 1996-98 winter
data suggest that a reasonable reliability limit for this kind of planning
study would be about 5,000 MW.
- Under less severe conditions, the operating limit would be
substantially higher. A frequency analysis can be done on this
data as on the other data.
- As a check, it would be useful to compare west side loads in January
1998 (the maximum in the data set used to derive the operating limits)
with the west side loads in February 1989 or December 1990 (with some
adjustment for load growth) or alternatively, the west side
temperatures for the two periods, to see if the data are
representative enough of the conditions we are seeking.
- Proposed mechanism: Make import capability from the south a
rough function of net west side load in ISAAC, using the regional
temperature data. Assume fixed import capability on the eastern
and northern interties.
Western market prices
Use HOSS output to define sustained peak, minimum generation and
instantaneous peak for the various hydro regulations for different fish
scenarios to use as input to Aurora. Aurora calculates western
prices and resources for input to ISAAC.
- Aurora is our only tool that allows an estimate of both 1) the
generation supply response as a function of market prices and 2) the
reliability level (calculated as reserve margin) as a function of
demand bids (captured in different costs for blocks of outage).
Basic analytical tool
Use ISAAC for basic analysis. The one dam model is probably
sufficient for the future value of water calculation (which requires
multiple passes through the future) rather than trying to modify ISAAC to
incorporate the full regulator for this function. ISAAC needs to be
modified to incorporate the full regulator for dispatch.
- ISAAC is being modified to do chronological dispatch for capacity
(replacing the current load duration curve method using Booth-Baleriaux
probabilistic capacity analysis. It is set up to do multiple
sub-daily periods (currently using four) chronologically over a
typical week.
- This approach would still use the trapezoid (described below), or
some other shortcut so as not to require a within-week regulation, as
HOSS does.
- ISAAC is being modified to dispatch with multi-area capability,
recognizing limited transmission constraints, captured as fixed
megawatt limits. Currently we envision two areas within the
Northwest: east and west of the Cascades.
- Are there others that would have a significant effect on the results
of this analysis?
Capacity modeling validation
For selected weeks:
1) Use the chronological multi-area ISAAC dispatch to estimate potential
hourly problems within the week. This will be based on an internal
redispatch of the output of the trapezoidal model, which calculates the
ability of the system to meet a sustained peak approximation of the hourly
load. The trapezoid is currently a stand-alone model but is to be
incorporated into ISAAC.
2) Hydro regulator output to HOSS. HOSS calculates ability of system
to meet actual hourly load for the week.
Compare HOSS and ISAAC output. Does ISAAC give a significantly
different answer about ability to meet the hourly load characterized in
the two different ways? A significant difference could come from
some sequential drafting problem through the week that forces misses of a
non-uniform daily pattern. Instantaneous lack of machine capacity is
another possible significant difference. Define adjustments that
might need to be made in interpreting ISAAC output.
- We may need to do this test for several different fish scenario
hydro regulations to ensure confidence in consistent similarities or
differences between HOSS and ISAAC.
An alternative to using the trapezoid is the function that relates
hydro sustained peak capability to monthly energy that is currently
contained in ISAAC.
The effect of extreme cold spells on side flows needs to be
established.
Analytical Flow Chart [graphic not
available]
Timeline [graphic not available]
Advisory Committee
- Dick Adams, PNUCC
- Ken Dragoon, PacifCorps
- Chris Elliot, NW Power Pool
- Rich Lauckhart, Northwest Power Enterprises
- Phil Sher, PNGC
- Carol Opatrny, PPC
- Audry Perino, BPA
- Linc Wolverton, ICNU
- Ed Clark, Ida-West Energy
|
- Jack Williams, OPUC
- Tim Smith, BPA
- Steve Kerns, BPA
- Ray Bliven/Don Shoenbeck, DSIs
- Marty Howard, CRITFC
- Steve Knutsen, PG&E Gas Transmission
- Marv Landauer, BPA Trans.
- Frank Afrangi, PGE Trans
- Lon Peters, PGP
|
^ top
|
|
|
|