March 20 – CBFWA staff will facilitate the initial Mainstem Systemwide Review Team (MSRT) meeting. The workgroup will review the process, schedule, and review criteria, and will identify work priorities for each compartment.
March 31 – The MSRT will develop a statement of priorities for each category within the Mainstem and Systemwide.
April 13, 14, 17-19 – Five days have been scheduled to review project proposals and apply the review criteria and assign proposals to prioritization categories. The reviews will be organized by category.
April 26 – CBFWA staff will accumulate all preliminary MSRT recommendations and submit them to Council staff.
May 9 – Council staff expect to present the preliminary MSRT recommendations to the Fish and Wildlife Committee at their meeting in Walla Walla, Washington for initial discussion.