Council receives CBFWA budgets |
May 15, 2002 |
|
ISRP releases final report |
June 7 |
|
Central staff prepares budget table:
|
June 10 to June 14 |
|
Review for programmatic and key project issues and begin developing rolling decision memo |
June 10 to June 21 |
|
Distribute ?base project/budget table?; sponsors submit corrections to base budget estimates |
June 17 to June 30 |
|
Central, state and CBFWA staff meet with project sponsors to discuss issues raised by ISRP report |
June 17 to July 12 |
|
Bonneville and NMFS provide comment on relation of proposed projects to ESA and other needs in the provinces (need this at least a number of days prior to the final state/tribal discussions that shape proposed workplans) |
June 10 to no later than July 19 |
|
Relevant state and tribal representatives develop proposed workplans and explanations from available provincial budgets, ?base projects? list and local priorities and ESA needs |
June 30 to July 31 |
|
Produce issue memo for upcoming Council meeting (August 13-14) that includes state/ tribal proposed projects on a subbasin-by-subbasin basis, draft budget tables, and discussions of any programmatic or key project issues |
August 7 (packet day) |
|
Fish and wildlife committee meeting to review issue memo, proposed workplans, draft budgets and programmatic and key project issues |
August 13-14 |
|
Revise issue memo into decision memo and prepare final draft budgets for Council's final decision at September 10-11 meeting |
September 4 (packet day) |
|
Council's final decision on project funding recommendations |
September 10-11 |