|
|
|
|
|
||||||||||||||
| Approved by Council to date |
37 |
| Pending for approval in late April |
13 |
|
Subtotal |
50 |
| Not likely to be in front of the Council until May or later |
9 |
| Subbasins where plans are not being developed: Bitterroot, Blackfoot and Clark Fork |
3 |
|
Total |
62 |
Level II groups and subbasin planners say it will take at least 14 months to develop a complete subbasin plan as we have defined it. If, for example, assessment work is already largely in place in a subbasin, then a shorter schedule may be possible. Staff encourages Council members and Level II groups to think critically about whether the remaining nine subbasins (Big White Salmon, Crab Creek, John Day, Klickitat, Lower Mid-Columbia Mainstem, Malheur, Owyhee, Palouse, and Sandy) can be completed by May 2004. This information will be the subject of a more detailed discussion with the Regional Coordination Group (Level III) on April 16.