nwcouncil home  

1994 Columbia River Basin Fish and Wildlife Program

Council document 94-55
space

 Fish and wildlife    Fish and Wildlife Program 

< Section 10 table of contents

10.8  Resident Fish Substitutions

and steelhead probably never will be able to return to some areas of the basin because of blockages by dams. These include the areas above Chief Joseph and Grand Coulee dams and the Hells Canyon Complex, as well as other smaller blocked areas. In its analysis of the contribution of the hydropower system to salmon and steelhead losses (see Council documents 87-15, 87-15A and 87-15B), the Council has addressed the extent to which resident fish substitutions should be used to mitigate losses of salmon and steelhead production in these areas.

      The Council has concluded that: 1) mitigation in blocked areas is appropriate where salmon and steelhead were affected by the development and operation of the hydroelectric projects; 2) to treat the Columbia River and its tributaries as a system, resident fish substitutions are reasonable for lost salmon and steelhead in areas where in-kind mitigation cannot occur; and 3) flexibility in approach is needed to develop a program that complements the activities of the fish and wildlife agencies and tribes and is based on the best available scientific knowledge. For substitution purposes, resident fish may include landlocked anadromous fish (e.g., white sturgeon, kokanee and coho), as well as traditionally defined resident fish species.

10.8A  Resident Fish Substitutions Policy

The substitution of resident fish to make up for losses of anadromous fish in areas now permanently blocked to salmon and steelhead reflects the Council's resolve to address complex, long-term problems. Historical records show that the Columbia River Basin Indian tribes relied extensively on salmon and steelhead, and the permanent loss of these resources has had incalculable impacts on tribal economies, cultures and religions.

      Historically, the Council approved projects in the areas above Chief Joseph/Grand Coulee, and in the blocked areas above Hell's Canyon Dam. Examples of substitution activities are at Lake Roosevelt, tributaries and reservoirs of Box Canyon Reach of the Pend Oreille River, tributaries of the Coeur d?Alene Indian Reservation, Kootenai River, lakes and streams of the Colville Indian Reservation, as well as above Hell's Canyon Dam on the Duck Valley Reservation, C.J. Strike Reservoir, the Fort Hall Reservation, and Cascade Reservoir. In the Council's 1993 resident fish and wildlife amendment process, the Council expanded its historic substitution areas to include projects outside of the historical blocks, above the blocked areas at Dworshak and Pelton dams.

      Substitution activities are one of the two highest priorities in the resident fish program, as provided in Section 10.1B.

      The Council has determined that until on-the-ground measures are achieved and the level of rebuilding is known, this priority is the best biological approach.

      The resident fish substitution policy is guided by and encompasses Sections 10.1, 10.1A, 10.1B and 10.2 of this program.

10.8B  Resident Fish Substitution Biological Objectives and Measures Above Chief Joseph/Grand Coulee Dams

The fishery managers, including the Colville Confederated Tribes, Coeur d?Alene Tribe, Kalispel Tribe, Kootenai Tribe of Idaho, Spokane Tribe and Washington Department of Fish and Wildlife collectively identified the following biological objectives as partial mitigation for the loss of anadromous salmon and steelhead blocked by Chief Joseph and Grand Coulee Dams. The Council approves these biological objectives and seeks implementation of the associated strategies and measures to achieve them, as a reasonable interim goal whose completion will partially offset the historic and contemporary losses incurred.

      The best available scientific information presented to the Council indicates that the full, complete and sustained achievement of the following biological objectives will redress approximately 10 percent to 13 percent of the total losses of anadromous fish previously harvested by the tribes above the block at Chief Joseph and Grand Coulee dams. Monitoring and evaluation of the performance of the strategies designed to achieve the stated biological objectives will determine the actual amount of credit to be applied to the underlying losses. The methodology for calculating the credit to be applied against the obligation of the hydrosystem will be developed as described in Measure 10.1D.1.

Lake Roosevelt biological objectives:

Species

Stock

Harvest goal (#)

Escape goal (#)

Total adult fish #

Total adult fish lbs.

Year

kokanee

hatchery

290,000

10,000

300,000

2.0

2000

Kokanee (adfluvial)

wild

120,000

60,000

180,000

2.0

*

rainbow trout

net pen

190,000

NA

190,000

1.5

1997

rainbow trout
(interim)
(adfluvial)

wild

12,000

6,000

18,000

2.0

2000

rainbow trout (adfluvial)

wild

150,000

74,000

224,000

2.0

finalt

walleye

wild

131,000

U

131,000

1.5

1996

NA = not applicable, U = unknown at the present time, * target date will be determined upon completion of baseline investigations, t = target date will be determined after interim goal is achieved.

Period

Elevation (feet above sea level)

Retention

January

1,270

45 days

February

Operate reservoir to elevation 1,260

40 days

March-April 15

Operate reservoir no lower than 1,250 feet above mean sea level

30 days

April 16

1,255

30 days

May

1,265

35 days

June-December

Operate reservoir at 1,288 (2 feet below full pool)

40-60 days or maximum historically achievable for each month

Strategies for achieving Lake Roosevelt biological objectives:

The following strategies will be employed to achieve Lake Roosevelt biological objectives:

Coeur d?Alene Reservation Tributaries biological objectives:

Biological objectives for wild adfluvial cutthroat trout in tributaries on the Coeur d?Alene Indian Reservation include rebuilding to 75 percent of the optimal level for adult fish. This will be accomplished by achieving interim biological objectives (25 percent and 50 percent of optimal level) by the target dates noted in the following table:

Tributary

Target level (percent)*

Escapement target

+Harvest target

=Biological objective

Year

Lake Creek

25

5,346

2,877

8,223

2001

 

50

10,695

5,751

16,446

2005

 

75

16,042

8,626

24,668

2009

Benewah Creek

25

9,277

4,880

14,157

2001

 

50

18,555

9,759

28,314

2005

 

75

27,832

14,648

42,471

2009

Alder Creek

25

7,562

4,113

11,675

2001

 

50

15,125

8,226

23,351

2005

 

75

22,687

12,339

35,026

2009

Evans Creek

25

5,420

2.944

8,364

2001

 

50

10,840

5,888

16,728

2005

 

75

16,260

8,832

25,092

2009

* Percent improvement over current conditions.

      Achievement of cutthroat trout biological objectives are related to enhancing habitat in each tributary to achieve the following conditions:

Lake Creek

Habitat Characteristics Current Condition Optimal Condition

Future Desired Condition (percent over current)

Difference

 

 

 

25

50

75

25

50

75

Average residual pool depth

 

1.9 ft

5.0 ft

2.4

2.9

3.4

0.5

1.0

1.5

Average canopy cover (thermal cover)

 

13.9%

75%

17.4

20.9

24.4

3.5

7.0

10.5

# Large woody debris/ Lineal distance

 

<0.1/m

 

 

 

 

 

 

 

Rifflepool ratio

 

3.6:1

3:2

3:1

3:2

3:2

-.6

-1

0

Average percent fines

19.1%

<10%

14.3

8.4

3.2

-4.8

10.7

-15.5

Benewah Creek

Habitat Characteristics Current Condition Optimal Condition

Future Desired Condition (percent over current)

Difference

 

 

 

25

50

75

25

50

75

Average residual pool depth

2.0 ft 5.0 ft 2.5 3.0 3.5 0.5 1.0 1.5

Average canopy cover (thermal cover)

36.6% 75% 45.8 56.4 65.6 9.2 18.4 27.6

# Large woody debris/ Lineal distance

<0.1/m  

 

 

 

 

 

 

Rifflepool ratio

1.8:1

3:2

5:1

3:2

3:2

-.3

0

0

Average percent fines

10.9%

<10%

8.1

5.3

5.3

2.8

5.6

0

Alder Creek

Habitat Characteristics Current Condition Optimal Condition

Future Desired Condition (percent over current)

Difference

 

 

 

25

50

75

25

50

75

Average residual pool depth

2.0 ft 5.0 ft 2.5 3.0 3.2 0.5 1.0 1.5

Average canopy cover (thermal cover)

23.8% 75% 29.8 35.7 41.6 5.9 11.8 17.7

# Large woody debris/ Lineal distance

<0.1/m

 

 

 

 

 

 

 

Rifflepool ratio

1.2:1

3:2

1.2:1

NC

NC

0

0

0

Average percent fines

37.6%

<10%

28.2

18.8

9.4

9.4

18.8

28.8

Evans Creek

Habitat Characteristics Current Condition Optimal Condition

Future Desired Condition (percent over current)

Difference

 

 

 

25

50

75

25

50

75

Average residual pool depth

2.5 ft 5.0 ft 3.1 3.6 4.3 0.6 1.2 1.8

Average canopy cover (thermal cover)

40.1% 75% 50 60 70 10 20 30

# Large woody debris/ Lineal distance

<0.1/m

 

 

 

 

 

 

 

Rifflepool ratio

10.9:1

3:2

7.9:1

5.3:1

2.6:1

-2.6

-5.3

-7.9

Average percent fines

16.8%

<10%

12.6

8.4

4.2

4.2

8.4

12.6

      Additionally, produce 25,000 catchable rainbow trout for stocking into trout ponds to provide an interim subsistence and recreation fishery for Coeur d?Alene Tribal members.

Strategies for achieving Coeur d?Alene Reservation Tributaries biological objectives:

The following strategies will be employed to achieve Coeur d?Alene tributaries biological objectives:

Biological objectives for kokanee salmon in the Kootenai River:

Stream

Type of Objective

Harvest pop#

+Escapement pop#

=Biological  Objective

Year Accomplished

Parker Creek

interim

0

350

350

2000

 

long-term

200

500

700

2008

Long Canyon creek

interim

800

800

1,600

2000

 

long-term

2,144

1,056

2,300

2008

Smith Creek

interim

100

500

600

2000

 

long-term

700

500

1,200

2008

Boundary Creek

interim

550

550

1,100

2000

 

long-term

1,474

726

2,200

2008

Strategies to achieve Kootenai River kokanee salmon biological objectives:

Biological objectives for largemouth bass, bull trout and cutthroat trout in the Box Canyon Reservoir and tributary streams:

These biological objectives are for the entire system. Specific interim and final targets for each tributary will be established upon completion of detailed habitat and fish population assessments that are currently under way.

Strategies to achieve biological objectives for largemouth bass, bull trout and cutthroat trout in Box Canyon Reservoir and tributary streams:

Biological objectives for lakes and streams on the Colville Indian Reservation:

Biological objectives for lakes and streams on the Colville Indian Reservation include production of 50,000 pounds of resident fish at the Colville Tribal Hatchery for distribution into reservation waters, including boundary waters, to provide a high quality subsistence/recreational fishery for Colville Tribal members as well as a non-member sport fishery. For the purposes of this program, a high quality fishery on the Colville Reservation is defined as: subsistence/ recreational fisheries that provide at a minimum 1 fish per hour catch-per-unit-effort and average fork lengths of 13.5 inches for rainbow trout (KFL 8 1.0), 12.0 inches for brook trout (KFL 8 1.0), and 20.0 inches for Lahontan cutthroat trout (KFL 8 0.9). Specific annual production targets include:

      Additionally, in reservation waters, increase natural production of brook trout by 10 percent and rainbow trout by 15 percent by 2000.

Strategies for achieving biological objectives for lakes and streams on the Colville Indian Reservation:

Biological objectives for Moses Lake and Ford Hatchery:

Specific biological objectives have not yet been identified for enhancing the warm water fishery at Moses Lake, pending recommendations of a baseline investigation being performed by the Washington Department of Fish and Wildlife. The biological objective for the Ford Hatchery is production of 35,000 additional pounds of resident trout for planting in northwest Washington lakes and streams.

Strategies for achieving biological objectives at Moses Lake and Ford Hatchery:

Measures and time frames for Resident Fish Substitution above Chief Joseph and Grand Coulee Dams:

The resident fish substitution projects for above Chief Joseph/Grand Coulee also include the operating criteria for Grand Coulee Dam described in Measures 10.3E.3 to 10.3E.5.

Bonneville

10.8B.1  Fund the following resident fish substitution activities and in the blocked area above Chief Joseph Dam to partially mitigate for salmon and steelhead losses incurred as a result of the construction and operation of Chief Joseph and Grand Coulee dams.

Spokane Tribe

10.8B.2  Operate and maintain kokanee salmon hatcheries at Galbraith Springs and Sherman Creek. Use the Sherman Creek hatchery as an imprinting site and egg collection facility to provide a source of kokanee fry for transferring to Galbraith Springs hatchery for rearing to the residualized smolt stage before planting into Lake Roosevelt. Coordinate decisions on hatchery production, stocking and outplanting locations through a three-member committee consisting of one representative each appointed by the Confederated Tribes of the Colville Reservation, the Spokane Tribe of Indians and the Washington Department of Fish and Wildlife.

10.8B.3  Add a new production well, capable of producing 2.5 to 3.0 cubic feet per second of additional flow, for the Spokane Tribal Kokanee Hatchery by January 1996. The purpose of this action is to allow for 500,000 kokanee to be reared to residualized smolt size at the Spokane Tribal Hatchery before release into Lake Roosevelt.

10.8B.4  The Council has been presented with evidence that kokanee released as residualized smolts contribute more to the fishery and return to egg collection sites at a higher rate than fish released as fry. In collaboration with the Washington Department of Fish and Wildlife and Colville Tribes, construct and operate 20 net pens for rearing kokanee salmon (25,000 fish/pen) to post-smolt size in Lake Roosevelt. This shall include 16 net pens, dock and anchoring system at Sherman Creek and four net pens at Seven Bays. Bonneville shall conduct an environmental assessment for the project in 1995, with construction in 1996.

10.8B.5  In collaboration with the Colville Confederated Tribes and the Washington Department of Fish and Wildlife, monitor and evaluate the Lake Roosevelt biota to assess the effectiveness of Measures 10.8B.2 to 10.8B.4, 10.8B.9, 10.8B.11 and 10.3E.3 to 10.3E.5 and determine impacts of reservoir operations on achieving the biological objectives addressed by these measures. Specifically, this measure will identify changes in the kokanee, rainbow and walleye fisheries as a result of the above measures and develop biological and integrated rule curves for Lake Roosevelt to define the operations necessary to sustain the resident fish populations. The following tasks will be completed as part of this measure:

 Colville Tribes

10.8B.6  Operate and maintain the resident trout hatchery on the Colville Indian Reservation. Monitor and evaluate this measure.

10.8B.7  In collaboration with the Spokane Tribe and Washington Department of Fish and Wildlife, evaluate natural production of kokanee above Chief Joseph Dam including Nespelem River, Big Sheep Creek, Alder Creek, Deep Creek, Orapaken Creek, Onion Creek and the San Poil River. The purpose of this measure is to evaluate the status of naturally producing kokanee, determine what measures are necessary to ensure self-sustaining populations and determine the feasibility of using these fish in the ongoing kokanee hatchery program in this area. The evaluation will involve electrophoretic evaluation, egg-fry survival determination, kokanee spawning escapement and kokanee entrainment. This project will be initiated in 1995 and completed by 2000.

10.8B.8  Identify and study the feasibility of alternatives for preventing resident fish from being swept downstream out of Grand Coulee Reservoir. This investigation will assess the number of individuals entrained, by species and life stage, at different seasons and under different operating conditions. It will also establish routes by which fish are entrained under different reservoir elevations and operating conditions. This investigation will be coordinated with the Lake Roosevelt Monitoring Program (Section 10.8B.5). Complete these studies and make recommendations to the Council by December 31, 1997.

10.8B.9  In collaboration with the Spokane Tribe and Washington Department of Fish and Wildlife, operate and maintain pilot projects for improving habitat and passage into and out of Lake Roosevelt tributary streams for rainbow trout. The aim of this measure is to emphasize natural production by: 1) facilitating passage of migratory rainbow trout between Lake Roosevelt and its tributary streams; and 2) improving fry and fingerling rearing habitat in these streams.

10.8B.10  In collaboration with the Spokane Tribe and Washington Department of Fish and Wildlife, monitor and evaluate effectiveness of the pilot projects in Section 10.8B.9 by trapping and marking adult and juvenile fish in tributary streams, estimating fish populations and habitat within the tributaries, and conducting creel surveys on each tributary. Contribution of these fish to the Lake Roosevelt fishery shall be determined by the Lake Roosevelt Monitoring Program (Section 10.8B.5). Pilot projects will be completed in 1995. Monitoring and evaluation will start in 1996 and continue to 2000. At that time, the Council will expect to receive a report that recommends one of the following alternatives: 1) continued operation and maintenance of pilot projects, plus improving habitat in additional tributaries if interim biological objectives of pilot projects are achieved; 2) additional monitoring, in the event the interim biological objectives are not met by 2,000 but there is reason to suspect they may be achieved in the near future; or 3) discontinue project if the interim biological objectives are not met and the reason for failure is understood and not correctable.

Lake Roosevelt Forum

10.8B.11  Implement the rainbow trout net pen rearing program in Lake Roosevelt including: 1) operation and maintenance of 26 existing net pens; and 2) procurement, operation and maintenance of 10 additional net pens. As a condition of Bonneville funding, operation of the net pen rearing program will be coordinated and consistent with the management policies of the Lake Roosevelt Fisheries Management Committee (see Section 10.8B.2), including those addressing stock selection and release strategies. In addition, continue voluntary contributions and private sector funding as a cost-share for the net pen rearing program.

Kalispel Tribe

10.8B.12  Design, construct, operate and maintain a warmwater low-capital bass hatchery on the Kalispel Indian Reservation. Mark all hatchery production. Design will commence in 1995, and construction will be completed by 1996.

10.8B.13  Design, construct, operate and maintain for two years, a yellow perch aquaculture facility on the Kalispel Indian Reservation. Design will commence in 1996, with construction completed by 1998.

10.8B.14  In collaboration with the Washington Department of Fish and Wildlife, conduct studies to determine the status of existing bull trout and cutthroat trout populations in the Pend Oreille River and its tributaries. Studies to be performed shall include: 1) determination of population densities, population abundance of each age class, growth, and feeding habits of bull trout in the Pend Oreille River and its tributaries; 2) radiotelemetry studies will be performed to identify migration patterns and areas that are utilized for spawning; 3) electrofishing, migration trapping and netting, in combination with mark/recapture investigations, will be performed to identify resident and adfluvial stocks that remain in the mainstem Pend Oreille and its tributaries; and 4) non-lethal biopsy samples will be collected to investigate genetic variability among different tributaries. This investigation will occur from 1995 to 1997.

10.8B.15  In collaboration with the Washington Department of Fish and Wildlife, complete advanced designs, and construct, operate and maintain habitat improvement projects to enhance bull trout and cutthroat trout in all tributaries in the Box Canyon Reach of the Pend Oreille River. Designs for three demonstration tributaries, Cee Cee Ah Creek, Skookum Creek and LeClerc Creek, will be completed in 1995, with construction occurring in 1996 and 1997. The remaining tributaries will be prioritized upon completion of Section 10.8B.14. The Washington Department of Fish and Wildlife and Kalispel Tribe will submit recommended habitat improvements, implementation schedules and detailed biological objectives for each tributary to the Council for approval in 1997. The Council will act promptly to consider these recommendations.

10.8B.16  Working with the U.S. Forest Service and Washington Department of Fish and Wildlife, remove exotic brook trout in Cee Cee Ah Creek in 1996.

10.8B.17  Design, construct, operate and maintain water control structures and repair dikes on the Pend Oreille wetlands wildlife mitigation project for the purpose of creating a bass nursery slough. Stock a portion of the bass production from the Kalispel Tribal hatchery (Measure 10.8B.12) into this slough in an attempt to cut hatchery production costs because fry can prey on natural foods. Screen the water control structures to prevent access by reservoir species that prey on bass fry. Design will occur in 1995, with construction and operation commencing in 1996.

10.8B.18  Construct and place artificial cover structures to increase the amount of bass fry winter cover in the Box Canyon Reach of the Pend Oreille River. Design will occur in 1995, with construction and placement of the structures in 1996 and 1997.

10.8B.19  In collaboration with the Washington Department of Fish and Wildlife, conduct a four-year monitoring program to assess effectiveness of bull trout and cutthroat trout habitat improvements in tributary streams and hatchery supplementation of largemouth bass in the Pend Oreille River. Monitoring will start in Cee Cee Ah, Skookum and LeClerc Creeks starting in 1998 (for cutthroat and bull trout) and in the Pend Oreille River in 1997 (for largemouth bass).

Coeur d?Alene Tribe

10.8B.20  Implement habitat restoration and enhancement measures in Lake, Benewah, Evans and Alder Creeks located within the Coeur d?Alene Indian Reservation including: 1) construct, operate and maintain water storage facilities adjacent to streams for water recruitment and to provide juvenile rearing habitat (trout refugia); 2) restore stream riparian zone through plantings, fencing and stream bank stabilization; 3) provide for off-site livestock watering areas; 4) construct lateral/side channels for juvenile rearing habitat and provide overflow or ?flood? channels to help relieve peak flow increases; and 5) place large woody debris in channels to increase instream cover.

      Also, 1) purchase critical watershed areas (riparian corridors, sensitive wetland and upland areas) for protection of fisheries habitat; 2) conduct an educational/outreach program for private landowners and the general public within the Coeur d?Alene Reservation to develop a ?holistic? watershed protection process; 3) develop an interim fishery for tribal and non-tribal members of the reservation through construction, operation and maintenance of trout ponds; 4) design, construct, operate and maintain a trout production facility on the Coeur d?Alene Reservation; and 5) implement a five-year monitoring program to evaluate the effectiveness of the hatchery and habitat improvement projects.

      Implementation of the above measures should be according to the following schedule: (i) in 1995, develop master plan and environmental assessment of the program, conduct habitat demonstration projects on Lake and Benewah Creeks and develop an educational outreach program; (ii) in 1996, complete master planning process and environmental assessment of the project, implement habitat improvement projects on Lake and Benewah Creeks, conduct an educational outreach program, advanced designs of hatchery and trout ponds and purchase land for hatchery and trout ponds; (iii) in 1997, construct and operate trout ponds and wells, begin construction of hatchery and well, implement habitat improvement projects on Lake, Benewah and Evans Creeks, continue educational outreach program; (iv) in 1998, continue hatchery and trout pond operation and maintenance, weir trapping of spawners, habitat improvements on Evans and Alder Creeks, and educational outreach program; (v) in 1999, continue habitat improvement projects, as well as operation and maintenance for hatchery, trout ponds, weir trapping of spawners and habitat improvement projects; (vi) from 2000 - 2004, monitor and evaluate restoration projects and (vii) for an indefinite period, continue to operate and monitor hatchery, trout pond and habitat improvement projects.

10.8B.21  Conduct a NEPA analysis, a habitat analysis and a land value appraisal of a 2,100 acre wetland/riparian and associated upland parcel in the Lake Creek drainage and Windy Bay area of Lake Coeur d?Alene in Fiscal Year 1996. This is to be credited for: 1) 250 acres of wildlife habitat losses due to Albeni Falls Dam (Table 11-04 in the Wildlife Section) on Lake Pend Oreille, an aboriginal use area of the Tribe, and 2) as a resident fish substitution for extensive salmon losses due to Grand Coulee Dam. Bonneville is to purchase a land option and transfer title to the Bureau of Indian Affairs to be put into trust for the Coeur d?Alene Tribe. In Fiscal Year 1997, complete the land purchase and begin habitat enhancement activities, initiating long-term operation and maintenance and monitoring and evaluation.

Kootenai Tribe of Idaho

10.8B.22  Perform a five-year Kootenai River ecosystem status determination and improvement study. The study should include elements that will: 1) provide a comprehensive ecosystem status report; 2) evaluate the biological feasibility of restoring system productivity; 3) identify effects of hydropower operations (Libby Dam) on aquatic biota and fish assemblages; and 4) develop, evaluate, test and analyze solutions to ecosystem problems caused by factors currently limiting system productivity, such as nutrient limitation and hydropower effects.

Washington Department of Fish and Wildlife

10.8B.23  Conduct baseline investigations to identify biological objectives for Moses Lake and determine the most feasible measures for enhancing the Moses Lake fishery to achieve these objectives. Include assessment of the current availability and use of spawning, rearing and cover habitats including hydrological and limnological factors associated with each as well as evaluating the age class structure, species composition and biological interaction occurring within the lake. The Council expects this investigation to start in Fiscal Year 1996 and be completed by December 31, 1998. The Department shall submit biological objectives and recommendations for fishery improvement to the Council for consideration in the next amendment process after that date.

10.8B.24  Improve water supply at Ford Hatchery to rear 35,000 pounds of resident trout and kokanee for stocking into Banks Lake and other northeastern Washington Lakes. Fund operation and maintenance cost for rearing these fish.

Washington Department of Fish and Wildlife and Appropriate Tribes

10.8B.25  Plan, engineer, design, construct, operate and maintain improvements to the Department's Phalon Lake wild rainbow trout trapping facility. These improvements will allow the continuation and possible expansion of the Kettle River wild rainbow stocking program into other upper Columbia River Basin waters.

Bonneville

10.8B.26  Fund a cooperative project among the Confederated Colville Tribes, Kalispel Tribe, Spokane Tribe, and the Washington Department of Fish and Wildlife to assess stock status of resident fish species and associated habitats in the areas above Chief Joseph and Grand Coulee Dams.

  1. Phase I. Assess existing data and develop a database, identify data gaps and develop standardized data collection methodologies.
  2. Phase II. Conduct field sampling to gather the needed data, assess data and identify management, protection and recovery efforts.
  3. Phase III. Implement management, protection, recovery, monitoring and evaluation.

10.8C  Resident Fish Substitution Projects Above Hells Canyon Dam

The following resident fish substitution activities and projects in the blocked area above Hells Canyon Dam will partially mitigate for salmon and steelhead losses incurred in this blocked area as a result of the construction and operation of hydropower projects in the Columbia River Basin.

Shoshone-Paiute Tribes

10.8C.1  Annually stock catchable and fingerling trout of the appropriate stocks in Duck Valley Indian Reservation lakes and streams.

10.8C.2  Review Duck Valley Indian Reservation surface water and groundwater suitability for resident fish production facilities. Initiate a comprehensive genetic sampling program of the redband trout in Owyhee Basin. Based on results of these studies, develop and implement strategies to protect wild redband trout populations from potential impacts caused by hatchery programs.

10.8C.3  Evaluate alternative sources of catchable and fingerling resident fish.

10.8C.4  Analyze feasibility of developing an additional lake fishery at Coyote Sink. Submit feasibility study with recommendations to the Council. Implement upon Council approval of recommendations.

10.8C.5  Implement, monitor and evaluate resident fish habitat improvement and protection measures at the Duck Valley Indian Reservation. Include the following habitat protection and improvement measures: 1) management recommendations for reservoir pool levels; 2) reservoir rehabilitation measures for non-game fish and aquatic vegetation control; 3) reservoir inlet and outlet screening; 4) improvement of recreational fishing sites; 5) stream riparian zone restoration by planting vegetation, fencing overgrazed areas and stream bank stabilization; and 6) base-line water quality survey to assess contaminants that may affect trout populations.

10.8C.6  Acquire or construct a trout production facility and operate and maintain the facility for the production of trout for stocking on the Duck Valley Indian Reservation and elsewhere. Assess opportunities for joint production strategies with the Shoshone-Bannock Tribe, including the training of tribal members in fish culture.

Bonneville

10.8C.7  Fund the Shoshone-Paiute Tribe projects listed above.

Bonneville, Bureau of Reclamation, Idaho Power Company, Fish and Wildlife Managers

10.8C.8  In cooperation with other relevant entities as listed in Section 3.1D, develop and implement the subregional process for the area above Hells Canyon Dam. Immediately meet to identify an approach for developing the subregional process, and identify funding responsibilities for developing the process. The process will identify funding commitments for additional resident fish substitution projects by Bonneville, by Idaho Power Company through hydropower project relicensing activities, by the Bureau of Reclamation through operation and management responsibilities, as well as by other appropriate parties. Additional resident fish substitution projects may include propagation and release of kokanee and coho stocks into Lucky Peak and Cascade reservoirs. Include in this process the development of a comprehensive approach to coordinating anadromous fish, resident fish and wildlife activities. Submit to the Council by December 31, 1994.

10.8D  Resident Fish Substitution Projects Above Dworshak Dam

Bonneville

10.8D.1  Fund the following resident fish substitution actions in the blocked area above Dworshak Dam to mitigate partially for salmon and steelhead losses incurred as a result of the construction and operation of hydropower projects in the Columbia River Basin.

Nez Perce Tribe

10.8D.2  Develop, maintain and manage trout ponds within the Nez Perce Indian Reservation including: 1) physically improve, maintain, monitor and stock two existing trout ponds; 2) identify through site inventory and analysis additional sites suitable for fish pond construction; 3) construct six to 12 additional fish ponds, depending on availability of suitable sites; and 4) maintain, monitor and stock the additional fish ponds.

10.8E  Resident Fish Substitution Projects Above Pelton Dam

Bonneville and Portland General Electric Company

10.8E.1  Fund resident fish substitution projects above Pelton Dam on an equal-share basis. These projects will partially mitigate for salmon and steelhead losses in this blocked area as a result of the construction and operation of hydropower projects in the Columbia River Basin.

Warm Springs Tribe

10.8E.2  Determine how the crayfish population in Lake Billy Chinook fits into the altered ecosystem. Include specific objectives of determining sex, size composition, growth rate and size at maturity of the crayfish population; size, relative abundance, and seasonal movement of the crayfish population; potential availability as a significant food item, especially for bull trout; and management recommendations.

< back  |  ^ top  |  next >