Draft Fiscal Year 1998 Annual Implementation Work Plan
General Policy Issues and Council Recommendations for Resolution
September 1997
[Note: The actual work plan has not yet been posted.]
Contents
- Artificial production (page 3)
- Comprehensive review of Columbia basin artificial
production (3)
- Interim review of production activities proposed
for funding/case-by-case review/ independent scientific review
(5)
- Captive broodstock projects (9)
- Lower Snake River Compensation Plan as a project
sponsor (11)
- Integrated Hatchery Operations Team (IHOT)
(12)
- Coded wire tagging (14)
- Habitat project selection criteria and procedure
(15)
- Increasing long-term operation and maintenance
costs/large capital construction costs (18)
- Research ? programmatic/ISRP issues (19)
- Competitive grants process (19)
- Mainstem habitat and population structure research
(20)
- Ocean/estuary research (24)
- Mainstem actions ? evaluation of assumptions and high-cost
programs in the mainstem (27)
- Evaluation of migration-related
assumptions/coordination of migration-related research (27)
- Peer-review of effectiveness of high-cost mainstem
actions, in general (28)
- Smolt monitoring program (29)
- Predator control program (squawfish) (30)
- Biological studies of gas supersaturation (31)
- Law enforcement (32)
- PATH/Bonneville non-discretionary (34)
- Projects subject to ISAB review in FY97: Lake Pend
Oreille Fishery Recovery Project and Hatchery PIT Tagged Chinook Study
(36)
- White sturgeon program ? various issues (37)
- Wildlife (39)
-
Monitoring and evaluation -- extend
to include some population monitoring (39)
- Acquisition of land and land easements (40)
- Information for the project selection process/coordinated
information service (41)
- Project selection process and information (41)
- Coordinated regionwide information service (42)
General Policy Issues and Council Recommendations for Resolution
1. Artificial production
a. Comprehensive review of Columbia basin
artificial production
Issue: The Council?s Program funds a number of artificial
production initiatives in the basin, including state and tribal efforts at
tributary production of anadromous fish and state and tribal resident fish
production in tributaries and in mainstem reservoirs. The federal
government funds a number of hatcheries in the basin independent of the
Council?s Program under the Mitchell Act, the Lower Snake River
Compensation Plan, and other programs. And there are still more artificial
production facilities funded by state governments, utilities and other
private entities.
A major concern is that these artificial production efforts do not fit
into a coherent, consistent and coordinated policy on the use of
artificial production. A call for a basinwide review of artificial
production has come from several directions. Section 7.0D of the Council?s
Fish and Wildlife Program calls for a comprehensive environmental analysis
of federal production activities. Federal agencies produced a draft
programmatic environmental impact statement on production activities
earlier this year, but the draft EIS failed to answer some of the major
questions about artificial production. Three independent scientific panels
(the Independent Scientific Group, the National Research Council, and the
National Marine Fisheries Service?s Snake River Recovery Team) have
completed reports over the last several years that call for a review of
Columbia Basin artificial production, all critical of current production
policy and noting the need to integrate artificial production with natural
production in a biologically sound manner.
The Independent Science Review Panel has added its recommendation that
the Council "implement a comprehensive review of artificial
propagation in the basin," covering "all propagation activities
including hatcheries funded by sources outside the Council?s
Program." The Council should not approve funding for the
"construction and operation of new artificial propagation
programs" until the comprehensive review of existing hatchery
programs "adequately addresses Measures 7.0D [comprehensive
environmental analysis], 7.1A [evaluation of carrying capacity], 7.1C
[inventory of wild and naturally spawning populations], 7.1F [systemwide
and cumulative impacts of artificial production], and until at least a
preliminary policy addressing Measure 7.1D [wild and naturally spawning
population policy] has been drafted." The Panel noted that resident
fish propagation facilities and projects should be included in the
comprehensive review. The Panel?s recommendation overlaps with the
language in the Senate appropriations committee report (not yet enacted
into law) calling on the Council to work with the Independent Science
Advisory Board [ The Independent Science Advisory Board (ISAB) was
chartered and appointed by the Council and the National Marine Fisheries
Service in 1995 to be available to provide independent science review of
particular issues as needed by the Council or NMFS. The Independent
Science Advisory Board evolved out of and replaced the Council?s
Independent Scientific Group (ISG). The Independent Science Review Panel
is the group specifically called for in the 1996 Power Act amendment.
Because of certain statutory requirements for the makeup of the Panel, it
was not possible just to name all of the members of the existing
Independent Science Advisory Board to the Panel when the Council needed to
first appoint the Panel. Instead, the two groups overlap substantially in
membership, but are not identical. The Council?s expectation is that
eventually we will have one group of independent scientists, serving the
functions of both the ISAB and the Panel.] to conduct a review of federal
hatchery programs and report to Congress by October 1998 with
recommendations for a coordinated production policy that aids fishery
restoration in a cost effective manner.
For this reason the Council, the Council staff and others have
discussed over the last several months how to organize a basinwide review
of artificial production. The Council?s staff?s most recent
description of how the review might be organized was in a July 30
memorandum from John Marsh to the Council ("Review of Columbia Basin
Artificial Production"). This memo discussed the possible scope and
elements of the review, how and who might organize it, possible schedule
and budget, and more.
Council recommendation: The Council recommends that a
comprehensive production review be conducted over the next year, and that
Bonneville reserve from $700,000 to $1,000,000 in the FY98 budget to fund
the review. The staff will work with the Independent Science Advisory
Board and others, as described in the July 30 memo (attached as an
appendix to this document), to design the review more precisely and
estimate its cost, returning to the Council in early October for review of
the design and approval.
The Council agrees with the Panel recommendation that all production
activities, including resident fish production, be included within the
comprehensive review. The Council recognizes that to be practical the plan
for the review might segment review of some production activities and
might not review all the minor production activities in the basin.
Finally, the Council emphasizes that the comprehensive review is to be
of all production in the basin, not just production activities
funded under the Northwest Power Act. This review will need active
cooperation and coordination with the federal agencies that oversee the
Mitchell Act, Lower Snake River Compensation Program and other federal
production activities. Funding for the review should be shared by the
federal agencies and not be paid for solely out of the Bonneville direct
program. Thus part of the process of designing the review should be
arranging a cost share. In addition, a basinwide comprehensive review of
production will have to at least take into consideration hatchery
production funded by entities other than the federal government, such as
hatcheries funded by utilities, and that these entities should also share
in the funding of the review. The means of reviewing this production will
be addressed during the design process.
b. Interim review of production activities
proposed for funding/case-by-case review/ independent scientific review
Issue: The issue that arises in light of the recommendation to
conduct a comprehensive review and reconsideration of production policy is
what to do in the interim -- how to respond to requests for FY98 funding
for production programs? The Panel recommended that while the
comprehensive production review is underway, the Council "not approve
funding for the construction and operation of new artificial propagation
programs in the FY98 program," with this exception:
"To prevent a complete moratorium on new production, the ISRP
recommends that the Council permit funding for an individual project only
if the project proponents can demonstrate they have taken measures 7.0D,
7.1A, 7.1C, and 7.1F into account in the program design and the Council
concurs. To ensure that standard is met, the individual projects should be
funded only after a positive recommendation from an independent peer
review panel."
The Panel added that "individual [resident fish] substitution
projects" should be reviewed "prior to authorization" by
this same "artificial production review panel." [ Resident fish
substitution projects in the Council?s Program are intended to develop
or enhance resident fish populations to mitigate for the loss of
anadromous fish by dam blockages, such as by Grand Coulee. See Council?s
Program, Section 10.8. Not all substitution initiatives involve artificial
production -- improving habitat to increase the numbers of a native
resident fish species to mitigate for salmon losses can be a substitution
project. The Council understands the Panel?s recommendation, at least
for the purposes here, to concern substitution by the use of artificial
propagation to introduce fish, especially non-native fish, into altered
ecosystems.]
The Council?s staff and others have outlined for the Council the
questions raised by the Panel?s recommendation -- the nature of a
moratorium or conditional moratorium and the legitimacy of holding up
funding for projects ready or nearly ready for construction funding; how
to organize such a review; how to determine which funding requests
represent "funding for the construction and operation of new
artificial propagation programs," etc. The Council?s staff has also
discussed with the Council and others a somewhat different way to approach
this issue, based on a multi-step review and approval process inherent in
any decision to initiate new production and the use of independent science
review in that process.
This issue has been the most controversial and the subject of the
majority of the comments received by the Council, especially concerns from
tribal representatives that production projects under the Program in which
they are involved have already been subject to intense scrutiny and need
not be subject to an additional independent science review.
Council recommendation: The Council recommends an approach to
this issue built upon the existing multi-step design and review process
recognized (directly and by inference) in the Program and used by
Bonneville for the design, review, approval and implementation of new
production initiatives. This is an interim approach intended to capitalize
on the existing procedures and standards in the Power Act as amended, in
the Council?s Program, and in the project review and funding process.
The comprehensive review of production policy may identify whether the
Council?s Program needs a new approach to production, with a revised
foundation and incorporating new procedures and standards, which would be
considered by the Council in a Program amendment process.
To summarize this recommendation: New production initiatives go through
a basic development process that has three main steps or components: (1)
conceptual planning, represented under the Program primarily by master
plan development and approval; (2) preliminary design and cost estimation,
as well as environmental (NEPA and ESA) review; (3) final design review
prior to construction. The Council, with the assistance of the agencies
and tribes, will identify which stage each production activity in the
Program is at. The Council will also identify how quickly a project is
moving through these stages, the nature of the review that the project has
already undergone, and the nature of the review commensurate with whatever
stage a project is in, including appropriate forms of independent science
review.
Based on this review, the Council will recommend funding only for the
activity specifically associated with the stage in the development process
where a project is located. For example, if a project has completed the
conceptual and preliminary design/NEPA review phases, but has not produced
final designs and cost estimates and received final design approval for
construction and operation, funding will be recommended only for final
design work, not for construction and operation. For a project at this
stage it may be appropriate, however, to set aside a construction funding
reserve or placeholder to be available once project approval obtained.
The Council also recommends making use of independent or peer review
for projects at each stage of the development process, although the scope
of the independent review and the questions asked of the review will be
different at the different stages, and presumably more limited in the
latter stages of the development and review process. To perform the peer
review function, the Council recommends naming a production peer review
group under the Independent Science Review Panel. To explain this peer
review recommendation in more detail:
Thorough independent scientific review of production initiatives is
especially appropriate during the early development stages, when the
scientific validity of a production proposal and its effect on the
environment should be most heavily scrutinized. Forms of independent peer
review may be utilized at these stages, although more needs to be done to
ensure a uniform review.
Many of the production projects that are part of the Council?s
Program are in or nearly in the final design/implementation stage. The
issue is whether and how to incorporate independent scientific review into
this third or final design review stage of the production projects prior
to beginning construction or implementation. If the development
review process has gone as it should have and included rigorous scientific
review at earlier stages, then the questions that should be relevant at
this latter stage involve fiscal and technical questions that are not
appropriate for independent science review. Still, independent scientific
review of a more limited type may be appropriate for projects at that
stage, essentially (a) to make sure that the project did indeed receive
the type of scientific scrutiny that it should have in the past to ensure
consistency with the policies in Section 7.1 of the Council?s Program
and elsewhere, and (b) to check whether changes in the project or in the
underlying science counsel further review, especially when there has been
a significant time lag between conceptual or preliminary approval and
final design review. A vehicle for this type of review has already built
into the new Power Act provisions for project funding -- the Act directs
the Panel annually to subject projects proposed for funding to independent
scientific review and to make use of peer review groups that the Council
may appoint to assist the Panel.
On this basis, the Council intends, in consultation with the Panel and
others, to name a production peer review group under the Panel as
authorized in Section 4(h)(10)(D) of the Power Act. Production initiatives
that are in the final design stage of the project approval process will be
reviewed by Council and staff, in consultation with the project sponsors
and other relevant entities, on a case-by-case basis to determine whether
final design review should be accompanied by a certain level of scientific
review, and whether that review needs to be assisted by the peer review
group. Assuming yes to both questions, the peer review group will be asked
to review the final design and the project history in an expedited fashion
and to advise the Council on specifically directed questions, such as:
- Has the project been through appropriate independent science review
in the past?
- Have the project sponsors demonstrated adequately in the past that
the project is consistent with the Council?s policies on
artificial/natural production in Section 7 (the specific concern of
the Panel)? If not, can these points be demonstrated now?
- Is the final design of the project consistent with any master plan
and preliminary design?
- If not, do the changes raise any underlying scientific questions for
further review?
- Has information about the project or its purposes changed in such as
way to raise new scientific concerns?
- Has the underlying science or the way it is understood changed so as
to raise new scientific issues?
- How technically appropriate are the monitoring and evaluation
elements of the project?
- Are there ways to obtain the same production benefits with
facilities that are lower in cost or less permanent should monitoring
and evaluation later indicate that the effort be abandoned?
The peer review group?s responses will be advisory; the Council will
consider but not be bound by positive or negative responses by the peer
review group. The Council?s review will be public, with an opportunity
for others to review and comment.
The Council is in the process of identifying which production projects
are at a stage where the project sponsors are proposing to implement new
production activities, defined generally to include projects seeking
funding to (a) construct significant new production facilities; (b) begin
planting fish in waters they have not been planted in before; (c) increase
significantly the number of fish being introduced; (d) to change stocks or
the number of stocks; or (e) change the location of production facilities.
These may not be the definitive criteria for defining "new"
production activity; the distinguishing criteria will be further examined
when the Council is ready to make a final determination of the status of
the projects. Anadromous fish and resident fish production projects are
both subject to this review. Based on the project descriptions, the
Council staff tentatively identified the following projects as possibly
within this category:
- Nez Perce Tribal Hatchery
- Grande Ronde NEOH outplanting and acclimation facilities
- Grande Ronde spring chinook captive broodstock facility
- Hanford K-Basin fall chinook acclimation facilities
- Wenatchee/Methow coho supplementation
- Johnson Creek supplementation facilities
- Umatilla satellite facilities
- Walla Walla facilities
- Yakima Hatchery facility construction
- Yakima River coho supplementation
- Yakima River fall chinook supplementation
- White sturgeon experimental aquaculture
- Coeur d?Alene fisheries enhancement -- production component
- Lake Roosevelt kokanee net pens
- Nez Perce trout ponds
- Lake Billy Shaw reservoir development
The other production projects funded under the Council program have
tentatively been identified either (1) as in the middle of planning and
design work, with no chance of implementation in FY98, or (2) as on-going
and not new production. It may be that some of the production projects on
the above list also fall into these latter two categories. The Council
will within three weeks of its decision on these general policy issues
review all the production projects and make a final recommendation as to
which projects are in the category of seeking and actually being able to
use funding in FY98 for new production activities and therefore subject to
review. For those within the category, the Council will also recommend the
nature and timing of the necessary review. The Council recognizes that
some of these projects may require review on an expedited schedule to
satisfy carefully considered biological needs, and the Council will take
what steps it can to assure that expedited review.
Finally, the Council agrees with the Panel?s recognition that some of
the best designed and implemented production projects in the basin are in
the Council?s Program. The Council is concerned that the Program
production initiatives are subject to this level of peer review and other
scrutiny for funding while other production activities in the basin (such
as the Congressionally funded production under the Mitchell Act, Lower
Snake River Compensation Plan and the Corps of Engineers mitigation
programs) are not. The Council recommends communicating to the NW
Congressional delegation and the federal agencies that in order to receive
federal funding these other production activities should undergo at least
the same level of scrutiny, including independent peer review, that the
Council, the states and the tribes ask of the production projects funded
under the Council?s Program through Bonneville?s direct fund. If and
when direct funding agreements between Bonneville and other federal
agencies bring other production activities within Bonneville?s direct
program fund, the Council expects that these production projects will
receive the same scrutiny and type of review that production initiatives
under the Council Program have received.
c. Captive broodstock projects
Issue: The production projects recommended for funding by the
Basin Authority include ten projects involving the study or use of captive
broodstock technology:
- One project is sponsored by the National Marine Fisheries Service is
the on-going systemwide assessment of captive broodstock technology,
seeking $1.25 million.
- Two more constitute the on-going Redfish Lake sockeye captive
broodstock, in which IDFG and NMFS seek $1.2 million in operation,
maintenance and evaluation funding. See Program Section 7.5A.
- Six others are the component parts of two captive broodstock
initiatives, one in the Grande Ronde River and one in the Salmon River
[ The Grande Ronde and Salmon River captive broodstock initiatives
were part of the supplementation project package (as #s 4 and 5)
reviewed by the Council in 1996. It is not stretching matters too much
to say that these were originally supplementation projects, at least
in large part, that changed during the review and approval process
into captive broodstock projects (due to the very weak status of the
runs in these two subbasins and due to the possible impact on listed
stocks), and that appear still to include elements of a
supplementation project as well as what might be thought of as a
"pure" captive broodstock effort.] :
- Three projects are components of the Grande Ronde spring chinook
captive broodstock effort sponsored primarily by ODFW, seeking
approximately $1.5 million in construction, operation and
maintenance and monitoring and evaluation funding, on top of
approximately $2 million allocated last year for design and
construction.
- Two make up the Salmon River spring chinook captive broodstock
program, sponsored primarily by IDFG and seeking more than
$200,000 for final design work this year, with a multi-million
dollar construction funding request due in the next year or two.
- One project seeks nearly $400,000 for operation and maintenance
of NMFS? Manchester captive broodstock facility that supports
both the Grande Ronde and Salmon River efforts.
- The last project is a listed stock gamete preservation effort in the
Salmon and Clearwater basins, sponsored primarily by the Nez Perce
Tribe and seeking $140,000 in operations funding.
The captive broodstock projects total more than $2 million in
construction and operations funding and are projected to stay at a
comparable level of funding well into the next decade.
The Council is concerned that a high-cost investment in the
implementation of captive broodstock techniques for Snake River spring
chinook is being recommended without proper review of the feasibility of
the technology. Section 7.4D. of the program calls on NMFS and Bonneville
to produce a scoping or feasibility study identifying captive broodstock
research needs, and then upon completion of the scoping study to fund
development of captive broodstock technology and implementation of captive
broodstock programs to aid in recovery of severely depleted stocks of
salmonids in the Columbia River Basin. Section 7.4D.2 calls on Bonneville
to fund captive broodstock demonstration projects identified under the
coordinated habitat and production process. In 1995 the National Marine
Fisheries Service completed "An Assessment of the Status of Captive
Broodstock Technology for Pacific Salmon." NMFS and Bonneville have
not reviewed with the Council the results of this study or its
implications for further work and funding. The 1995 assessment is full of
cautionary remarks to the effect that captive rearing of Pacific salmon is
"problematic," and "experimental," its "success
is uncertain," and the existing captive broodstock programs
"have not been thoroughly evaluated," even as it concluded that
it is worth exploring whether the technique might help forestall
extinctions in certain geographical areas. Other management entities have
raised concerns about the extent to which high-cost implementation of
captive broodstock activities have gone beyond the experimental status of
the technique and have gotten out of sequence ahead of the need for
further feasibility evaluations. The Panel criticized the high priority
placed on captive broodstock programs in the managers? recommendations
(ISRP report at pg. 33), although the Panel did not make this the subject
of one of its specific recommendations.
For these reasons the Council and its staff have been raising concerns
with the captive broodstock implementation and assessment projects as part
of a Program consistency review. The issue has been clouded by confusion
over whether these are Endangered Species Act projects and thus not funded
through the Power Act as part of the Council?s program. These are not
ESA projects. Although part of the draft Recovery Plan and the Biological
Opinion for federal agency production activities, captive broodstock
activities are not part of the reasonable and prudent alternatives in NMFS?
hydropower Biological Opinion under the ESA, and thus are not imposed on
Bonneville under that Opinion. The projects are being funded as part of
the Council?s Program.
Council recommendation: First, the Council recommends that the
captive broodstock projects be categorized along with the other production
projects in terms of the development review process discussed above.
Continue funding the sockeye activity and the planning and design work for
the Grande Ronde and Salmon River projects. Construction and operation
funds for these latter two sets of projects should be held in reserve
pending further evaluation of the feasibility of captive broodstock
technology by the Council, in consultation with NMFS and the state
agencies and tribes, and with the assistance of the production peer review
group described above. Due to the pending construction status of the
Grande Ronde facility, the Council will expedite its decision on review of
this project.
With regard to the systemwide assessment project, the Council is
concerned about the increase in the budget for this project and about the
nature of this project in relation to 1995 assessment produced by the
National Marine Fisheries Service. The Council recommends that funding for
this project be reserved pending a review by NMFS with the Council of the
budget and scope for this project and the feasibility of the technology.
d. Lower Snake River Compensation Plan as a
project sponsor
Issue: The FY98 production projects include seven
supplementation/captive broodstock projects that list the Lower Snake
River Compensation Plan as a "sponsor." It is not clear why the
LSRCP is listed as a "sponsor," rather than the Fish and
Wildlife Service, the agency that manages Compensation Plan activities.
LSRCP activities are funded by Congress and reimbursed by Bonneville in a
different budget category from the direct program. Bonneville, the Fish
and Wildlife Service and others are engaged in discussions about shifting
the LSRCP activities to a direct funding arrangement, using the same money
but just reallocated to a different category and method of funding.
The Council?s concern has been whether these projects represented
LSRCP activities encroaching on and demanding a share of the existing
direct program funds, while also carrying an outside-the-Power-Act,
non-discretionary status. After further review, the Council is comfortable
that the projects involved here are not core LSRCP production activities
moving into the direct program, and that there does not appear to be an
"in lieu" problem under the Act, or a problem under the
Bonneville budget Memorandum of Agreement that allocated budget amounts to
the different category. Six of the seven projects are part of the new
supplementation initiatives approved in 1996. They appear to have received
the additional LSRCP label because the U.S. Fish and Wildlife Service
provided some assistance in design, review and construction funding. But
the Service has done so always with the understanding that these
activities are part of the direct program and not the distinct LSRCP
activities and funding. The seventh project funds monitoring and
evaluation of Snake River fall chinook above Lower Granite, apparently an
activity that is associated with assuring that production and
supplementation projects do not adversely affect the listed fall chinook
and which the Service has not intended to cover and cannot cover out of
the funding for its traditional LSRCP activities.
Council recommendation: Despite what the label says, these
projects are Power Act projects funded by Bonneville through the Council?s
Program and Bonneville?s direct program fund. The fact that these
projects carry the LSRCP as a sponsor does not give them a particular or
distinct status within the direct program. These projects are
discretionary projects subject to project review.
The possibility of direct funding LSRCP activities in general is a
separate issue that is under regional discussion.
e. Integrated Hatchery Operations Team (IHOT)
Issue: The Council?s Program created the Integrated Hatchery
Operations Team (IHOT) to develop standards and criteria to improve
existing hatchery production. The Program then calls on Bonneville to fund
independent audits of existing hatcheries to determine if they are
operating consistent with the reformed hatchery standards and criteria.
The Program asks IHOT to review the hatchery audits, develop
recommendations for corrective actions, and report annually to the Council
and others. See Council?s Program, Sections 7.2A, 7.2B. IHOT has
been working with the independent auditor to review the hatchery audits.
For the FY97 budget, the Council recommended that funding for IHOT
remain at the $465,000 level, with the expectation that IHOT would use
those funds to complete the review of the hatchery audits. The
hatchery audit review could not be completed this year, primarily because
the audit contractor working with IHOT was still completing its work
product for final IHOT review.
For FY98, IHOT requested another $635,000, which the Columbia Basin
Fish and Wildlife Authority reduced to $465,000. Completion of the audit
review appears to be most of what these requested funds will be used for.
One issue is why additional funds are needed to complete the audit review.
Another has been whether IHOT has any other role in the emerging effort
for a comprehensive review of hatchery policy.
Council recommendation: The Council does not recommend
another block of funding for IHOT, what has been essentially a funding of
delegated staff position and not tasks, to complete the review of hatchery
audits. The Council recommends instead:
First, the Council staff, hatchery managers, and Bonneville are to work
together to identify what work still needs to occur to finish the audit
process. The Council expects this to include two tasks: (1) Complete the
audit reviews. (2) Recommend a procedure to ensure that the audits and
audit reviews will be made available to the hatchery managers, to guide
the managers in making any needed reforms in their operations, including a
reporting element to assure accountability. The staff and the others are
also to estimate what it would cost to complete these two tasks on a
task-and-time accounting method, using the most cost-effective approach
possible. This may mean continued use of all or some of the IHOT personnel
or through some other type of contractor.
Bonneville is then to determine whether funds remain available from the
FY97 budget to fund these two tasks. If more funds are necessary to
complete the reviews and develop the procedure for using the audits,
return to the Council for review and a funding recommendation with a
description of what work needs to be funded, who will do the work and what
the additional amount is.
The Council expects in future years that hatchery operations funded
through the Council Program will explain how they have responded to the
hatchery audits to justify continued operations funding. The Council also
expects that the comprehensive review of artificial production will review
and produce recommendations about operations at existing hatcheries, the
value of the current standards and criteria for those operations, and the
value of continued hatchery audits and audit reviews.
f. Coded wire tagging
Issue: Bonneville is projected to spend approximately $2.8
million on coded-wire tagging and recovery in FY98. Tagging throughout the
basin and coast-wide has primarily benefited the states? harvest
regulation activities, not an area of Power Act/Council concern or
authority, although in the last few years the information apparently has
also been used to track the impact of production facilities in a broader
sense. The Council?s program calls for some marking of hatchery salmon,
in Section 8.4C. The issue is whether the level of Bonneville funding for
coded wire tagging is out of proportion with what could be considered
Bonneville?s "fair share" of the coded wire tagging program,
whether that share is based on the proportional number of fish from direct
program-funded hatcheries that must be tagged or on the amount of
information gleaned from the tags that is relevant to the Council?s
program.
Council recommendation: The Council recommends that funding be
approved as proposed for FY98. The Council?s staff is in the process of
fleshing out the details of the coded wire tagging funding by Bonneville
and the policy implications underlying any calculation of what would be
Bonneville?s "fair share." The Council will work with
Bonneville and the affected agencies and tribes to review the program over
the next year in an attempt to determine Bonneville?s fair share of the
program?s costs in future fiscal years, and to determine how the
information from the tagging is relevant to the Council?s Program.
2. Habitat project selection criteria and procedure
Issue: It has long been a goal of the Council?s program to
develop a more coordinated and guided process for determining how to
invest Bonneville funds in tributary habitat and watershed improvement
projects. See Program Sections 3.1D, 7.0B. 7.0C, 7.6. The Panel?s
recommendations are consistent with this goal. The Panel recommended that
habitat policies and objectives be established for each subbasin and
coordinated with production goals, that development of reliable watershed
assessment procedures be given high priority, and that the watershed
assessments precede implementation of restoration projects. When
discussing the resident fish portion of the Council?s Program, the Panel
similarly recommended that the Council require a basin-wide systematic
inventory of native resident fish populations and their status,
assessments upon which "opportunities for restoration and rebuilding
native resident fish populations can be identified and prioritized."
With certain exceptions (e.g., the Hungry Horse mitigation program in
Montana), funding for stock and loss assessments for resident fish has
been minimal, due to an understandable desire to direct money to
mitigation efforts and not evaluations. But the Panel wondered "how
restoration opportunities for native resident fish can be identified and
prioritized without having completed a basin-wide inventory of resident
fish populations and their status."
The fish and wildlife agencies and tribes, the Council staff and others
are in the process of developing both a procedure and criteria for
evaluating and selecting watershed habitat projects for funding. The
Independent Science Advisory Board recently reviewed draft criteria, and
had both praise and criticism. The Council is awaiting further review by
the fish and wildlife managers in response to the Board?s review. The
criteria and selection procedures will not be ready for Council review
until late fall at the earliest. Selection of habitat projects for FY98
funding is not likely to occur until early 1998. Money will need to be
reserved to fund the set of habitat projects to be selected later in the
fiscal year. Agency and tribal managers in general agree with this
approach, although some are concerned about losing the certainty of
selecting projects and beginning the contracting of these projects at the
start of the fiscal year. Also, this has been primarily an effort of the
anadromous fish managers. It is the sense of the Council that the habitat
criteria development and watershed assessment efforts should incorporate
resident fish as well as anadromous fish, both in the shared streams below
the blocked areas and in the resident fish-only areas above the blockages.
This is consistent with Sections 10.1 and 10.2 of the Council?s program,
which call for the application of watershed principles and coordinated
habitat procedures and objectives in the resident fish program.
Council recommendation: The Council concludes that the
development of the habitat/watershed criteria and procedure is consistent,
so far, with the policy direction in the Council?s Program and with the
Panel recommendations. The Council recommends this process continue and
that funding for habitat projects be deferred until the development of the
criteria and then its application to select projects for funding. The
Council also agrees with the Panel that watershed assessments must guide
the selection of habitat projects; the Council understands watershed
assessments to mean assessments which describe the habitat conditions in
the relevant watershed and the needs and opportunities for habitat
restoration for the stocks inventoried in that watershed. The Council also
agrees that stock and hydropower loss assessments for the resident fish
part of the Program need greater attention than they now have, and that to
be consistent with the Program and the Panel?s general recommendations,
stock and loss assessments for resident fish should be developed not in
isolation but as part of watershed assessments. The development process
for the project selection criteria and procedures needs to integrate the
resident fish and wildlife parts of the Program.
Based on these considerations, which are derived largely from the Panel?
report and the ISAB?s review of the draft criteria, the Council
recommends the following guidance to those developing the habitat criteria
and procedures:
- Watershed assessments should precede implementation of restoration
activities, with limited case-by-case exceptions. The watershed
assessments will provide better understanding of the needs of each
watershed, allowing for prioritization of projects within each
watershed. It is likely that much of the relevant information and even
assessments already exist or are in development, through the subbasin
planning process that has been part of the Council?s Program since
the 1980s, on-going Program assessments in the resident fish areas,
the Interior Columbia Basin EIS analysis, the local watershed
initiatives around the basin, and more.
- The watershed assessments and the habitat project selection criteria
and procedures should take into account all of the fish and wildlife
values and needs of a watershed, including resident fish and wildlife
and not just anadromous fish.
- The Council?s goal is the development of integrated or coordinated
habitat project selection criteria and procedures to be used to select
all habitat projects funded under the Program, whether for anadromous
fish, resident fish, wildlife, or some combination of these. The
Council understands that the draft criteria have, so far, been the
product primarily of the anadromous fish managers, and thus that one
of the next steps is for them to work with the resident fish and
wildlife managers to agree on criteria acceptable to all managers.
Also, the Council does not mean that all the three types of projects
must be evaluated against each other under one unified set of
criteria. The development process should yield criteria and procedures
that are integrated in certain ways but also coordinated and distinct
in others. The Council expects that the development of integrated or
coordinated criteria and procedures will not affect the application of
the current budget allocation between anadromous fish, resident fish
and wildlife as described in the Council?s Program.
- The habitat project selection criteria and procedures should allow
for evaluation of projects not just within a subbasin but also between
subbasins. That is, the procedure should allow the managers and the
Council to identify which basins provide the best opportunities for
investments to protect and restore populations.
- If the project selection procedure chosen allows for a policy- or
management-level review and prioritization by the managers after
projects are evaluated on the basis of technical criteria, the
procedure must provide clear standards and explanations for how that
management review has altered the technical evaluations.
- The habitat project evaluation and selection process should include
provisions to ensure that StreamNet is used to coordinate, accumulate,
store and make available the relevant watershed information,
assessments and projects. The Council recommends that approximately
$100,000 of the reserved habitat funds be dedicated to this purpose.
On-going or new assessments seeking funding, such as the Kalispel
Tribe stock assessment study proposed for funding in FY98, should be
coordinated through Streamnet with this broader effort.
- The Council further recommends that funding for all of the
tributary/watershed habitat projects, both existing and newly
proposed, be held in reserve and the projects be placed into the
habitat project selection process for review when it is developed.
This applies to anadromous fish, resident fish and wildlife projects.
The Council recommends three exceptions to this general rule:
- To avoid jeopardizing funds already invested, the Council recommends
that FY98 funding for maintaining existing projects be
authorized at the start of the fiscal year, as interim protection for
these projects pending completion of the habitat project selection
process. The Council will work with Bonneville, the managers and the
project sponsors to determine the appropriate level of maintenance
funding.
- Projects that fund the regional irrigation diversion screening
program should continue. This program is substantially funded by
Congress under the Mitchell Act, and the Council recommends that
projects linked to this program continue as proposed due their
function in supplying the screens for the Congressionally appropriated
regional program. The Council also recommends approval of the funding
for the Yakima Phase 2 screens.
- Finally, the Council recommends interim funding for watershed
coordination.
The subbasin-by-subbasin/project-by-project guidance that follows will
identify what maintenance, screening and coordination funding is involved.
The exceptions do not mean these projects will not be reviewed as part of
the project selection process, only that the Council recommends funding
continue in the interim.
The final issue is the amount of FY98 funds to be reserved for habitat
projects. The recommended reserve amount will be a combination of the
amount already identified by the fish and wildlife managers for habitat
projects plus whatever amounts the Council recommends be allocated to
habitat projects from the total amount that may be available after
reductions in other areas. The Council expects to preserve the Program?s
overall budget allocation while identifying the amount reserved for
habitat projects. The Council will make a final recommendation of a
reserve amount after further review of the FY98 budget allocation. The
Council expects the amount to be available for habitat projects to be
approximately [$15 million? 20 million?].
3. Increasing long-term operation and maintenance
costs/large capital construction costs
Issue: The Council identified two general issues regarding
operation and maintenance costs for production and habitat projects.
First, a number of the on-going production projects show a substantial
increase from what was projected in FY97 to be the FY98 operations and
maintenance costs and the subsequent FY98 request for operations
and maintenance funding. A few habitat projects show operations and
maintenance increases of similar magnitude. A broader issue is that the
funding of major new production programs (especially) and habitat work
means that the Council?s Program is creating an ever increasing
obligation for funding operation and maintenance, which may not be
adequately accounted for and described. The issue for the Council has been
how to define what are appropriate operations and maintenance costs and to
ensure that long-term operations and maintenance obligations are
accurately described and understood. In addition, some projects have
committed and propose to commit significant amounts of the Bonneville
direct capital. For example, $12 million in capital funds are recommended
in FY98 to complete facilities at the Cle Elum hatchery.
Council recommendation: Project specific operations and
maintenance issues and explanations are provided in the project-by-project
guidance that follows. Also, the Council expects that more rigorous
attention by the Council during the final design phase of production
projects, as described above, will help ensure more complete and clear
operations and maintenance expectations.
More important are three general points: First, the Council recommends
that the operations and maintenance costs set forth in the project
descriptions by the project sponsors and the CBFWA draft work plan be
treated by Bonneville, the managers and the project sponsors as estimates,
and not as the amount of money to be allocated or reserved to the
project for operations and maintenance expenses. The actual budget
allocation for operations and maintenance expenses should be determined
during contracting for the project by Bonneville and the project sponsor
with review by the Council.
Second, the Council recommends that Bonneville work with the Council
staff and the project sponsors to develop better long-term operations and
maintenance projections for projects prior to next year?s funding
process. The Council requests a report midway through this fiscal year on
long-term operations and maintenance expectations. This tasks includes
agreeing to standards as to what are appropriate expenditures for
operations and maintenance.
Third, for FY98 the Council recommends fiscal review by the Council of
the any project that will commit a significant amount [5 million?]
of Bonneville direct capital before the Council will make a final
recommendation on the funding for that project in FY98.
4. Research ? programmatic/ISRP issues
a. Competitive grants process
Issue: The Independent Science Review Panel recommended that the
Council "implement a competitive grants program" for selecting
research projects for funding, a key element in a set of recommendations
intended to inject a greater degree of independent peer review into the
project selection process. While the merit in this proposal is obvious, so
are some of the drawbacks, including the possibility of an excessive
expense of money and time developing and operating a competitive grants
process.
A related point emphasized by the Panel is that research, monitoring
and evaluation activities need to be better coordinated, integrated and
prioritized across the Council?s Program and between the Council?s
Program and other research activities in the basin. The development of a
coordinated research, monitoring and evaluation framework is needed, a
process already begun in connection with the multi-year implementation
planning process over the last year.
Council recommendation: The Council recommends the development
of a competitive grants program for funding research projects in FY99,
pending Council review and approval of the design and budget for such a
process. The Council?s staff is to work with the Panel, in consultation
with the agencies and tribes, the National Marine Fisheries Service and
Bonneville, to develop a proposal for such a process and its estimated
cost, with the aim of submitting the proposal to the Council in late fall.
One issue to be worked out in developing the proposal will be the
relationship between a competitive grants process for research projects
and the Power Act provisions for annual review of projects recommended for
funding by the Panel. This may mean, to avoid duplication, that the Panel
or a peer review group under the Panel should conduct the competitive
grants process.
Another relevant issue concerns who will define research needs for the
competitive research grants process and how. By the FY99 project selection
process the Council expects not only to develop a competitive grants
process but also at least an interim or preliminary coordinated research,
monitoring and evaluation framework to identify priority research needs
for the project selection process. The Council recommends that the
Council, the Independent Science Advisory Board, and the fish and wildlife
managers work together to define the interim research framework and the
research needs and the requests for research proposals. This will be an
interim research framework because a more comprehensive framework may take
longer to develop than is possible for the FY99 funding process, and
because developing a research framework could be influenced by a Council
Program amendment process.
The Council is recommending that a relatively small amount of FY98
funds be reserved for scoping/initiating three new research activities.
The Council also recommends that its staff work with the Panel to develop
a bid process to select the people who will undertake these studies.
b. Mainstem habitat and population structure
research
Issue: The issue for the Council is whether to recommend that a
reserve amount set aside to initiate a research project or projects to
assess mainstem habitat and population structures. Section 7.1A of the
Program calls for an evaluation of the conditions, ecology, carrying
capacity and limiting factors in the mainstem. This has become more
critical now, given that in response to a Council program measure, the
Independent Science Group (now the Independent Science Advisory Board)
proposed in its scientific review of the Council?s Fish and Wildlife
Program, Return to the River, a conceptual scientific foundation
for the Council?s Program that pays special attention to mainstem
habitat conditions. The Return to the River report recommended that
a critical component of Columbia River salmon restoration should be
protecting and restoring mainstem habitat, especially mainstem spawning
and rearing habitat for core populations in a metapopulation structure,
habitat that has been destroyed, inundated, blocked or degraded by
mainstem hydropower development. If mainstem habitat and metapopulation/core
populations structures are indeed critical to Columbia River salmon
restoration work in the future, and thus to the Council?s program during
a Program amendment process, more needs to be learned about the nature of
Columbia River mainstem habitat, how productive it was and where, what was
the population structure in that habitat, how the hydropower system
damaged that habitat and the population structure, what might be done to
protect and restore mainstem habitat, and what might be the affect on
population structure.
The Panel was critical of the fact that none of the mainstem research,
analysis and monitoring and evaluation in the program is directed toward
this priority and the wide array of mainstem habitat characteristics that
need study. The Panel recommended that funds be set aside for what they
called a risk-benefit analysis of tradeoffs to create mainstem habitat and
a food web quantification analysis.
Council recommendation: Return to the River raises
important questions about mainstem habitat conditions and mainstem
population structure. To help the Council and the region evaluate these
questions, the Council recommends that an amount of money be set aside for
two studies, one on mainstem habitat and one on population structure,
briefly described below. What the Council recommends here are studies that
involve primarily a review of existing research literature and then
analytical work based on that review, not extensive ( or even any) new
field work research. The studies should also be developed to capitalize on
related work going on in the basin and to be coordinated with those
efforts. The Council recommends that significant funds not be allocated to
new mainstem habitat research initiatives until the studies described here
are completed and reviewed. The Council directs its staff to work with the
Independent Science Advisory Board and others to produce a more formal
description of these study proposals and competitive bid process to select
who will undertake the described studies. The two studies are as follows:
Assessment of the impacts of development and operation of the
Columbia River hydroelectric system on mainstem riverine processes and
salmon habitats
Development of the Columbia River hydroelectric system has
significantly altered the character of the Columbia River. Major areas
were blocked to passage of anadromous fish, riverine processes were
disrupted, habitats were eliminated or greatly modified and river foodwebs
and ecological processes were modified. Recent scientific syntheses
regarding fish recovery in the Columbia River have emphasized the
importance of the mainstem areas and normal riverine processes. Proposals
are now being considered to return a portion of the lost habitat by
breaching or drawing down mainstem hydroelectric projects. However, to
date, no systematic assessment has been made of the extent and types of
habitat modifications that have occurred, potential locations for
restoration or of the potential benefits.
This project would assess the extent of riverine habitat lost to
development and operation of the Columbia River hydroelectric system and
the types of ecological modification that have occurred, and suggest areas
or actions with particular potential for restoration of riverine habitat
and processes. The assessment should describe the historical use of the
mainstem river by chinook and other species and estimate the amount of
habitat lost as a result of development and operation of the hydroelectric
system. Impacts of the hydroelectric system should include habitat
blockages as well as habitat and ecological modification in areas still
accessible to anadromous fish. The project would rely largely on existing
information sources; no new fieldwork is envisioned at this stage.
Development of information relating to mainstem habitat in the area of the
four Lower Snake River projects should be coordinated with ongoing studies
by the U.S. Army Corps of Engineers. Information should be organized
within a Geographic Information System, which also might be used to
examine the impacts of drawdown or other mitigation strategies. The
project should also propose and assess options for testing riverine
habitat restoration hypotheses, especially drawdown of one or more
mainstem reservoirs.
Specific objectives:
- On the basis of an assessment of historical records and photographs,
identify the amount of mainstem river fish and wildlife habitat lost
as a result of development and operation of the Columbia River
hydroelectric system.
- Building on recent scientific assessments, identify historical
"hot spots" for salmon spawning and production that existed
prior to development of the hydroelectric system, especially those
that existed below the present limits to anadromous fish passage.
- If possible, assemble the above information as a Geographic
Information System. To the maximum extent, make use of the existing
resources of the StreamNet system.
- Develop a list of options for restoration of mainstem habitats for
salmon in the area below the present migration limit for anadromous
fish and for resident fish in areas above this point.
- Identify opportunities to test strategies for restoration of
mainstem habitat.
Application: This project is intended to contribute to regional
discussions regarding restoration of mainstem habitats including
development of the Council?s Fish and Wildlife Program. It should also
contribute to the assessment of losses of fish and wildlife in the
Columbia River Basin resulting from development and operation of the
hydroelectric system.
Suggested budget estimate: $200,000
Assessment of population structure in Columbia River chinook
salmon and its application to existing populations
Population structure is based on the extent and nature of genetic
communication between populations and natural selection exerted by the
local environment. The existing population structure of chinook salmon in
the Columbia River reflects the progressive fragmentation and degradation
of habitat and is likely a remnant of a more continuous and connected
historical population structure. To the extent that population structure
is an adaptive trait (i.e. is the result of natural selection and is a
species adaptation to particular habitats and environments) understanding
changes in population structure and the relationship of past and present
structure to habitat conditions could be a key to restoration of salmon
throughout the basin.
This project would assess the application of theories, such as the
metapopulation concept, to chinook salmon population structure in the
Columbia River and the relationship to habitat structure and variation. It
would then examine how population structure concepts would apply to fish
recovery efforts in the Columbia River Basin. Finally, it would assess the
value and possibilities for restoration of a suitable population
structure. Initially, the project should focus on the likely nature of
chinook salmon population structure in the Columbia River including the
applicability of the metapopulation concept. It should rely heavily on
existing data sources and literature to describe the possible population
structure in existing chinook salmon populations. A later phase could test
this description through field studies or other methods.
Specific objectives:
- Review of literature and research pertaining to fish population
structure including metapopulation theory and its application to
Pacific Salmon and other fish species.
- Assessment of the application of a population structure concept to
Columbia River salmon and other fish species.
- Development of a conceptual description of fish population structure
for Columbia River salmon and other fish species including the
relationship of this structure to spatial and temporal habitat
variation.
- Bench testing of the concept using existing inventories of salmon
and other fish species in the Columbia River Basin. This phase should
utilize the resources of the StreamNet system whenever possible.
- Recommendations regarding the utility of using population and
habitat structure as a basis for structuring recovery efforts of
salmon and other fish species in the Columbia River Basin.
Application: Results from this study would contribute to the
development of a scientific foundation and framework for the Council?s
Program and other regional efforts. It should help to structure these
efforts and identify suitable conservation and management population
units. It would also help to formulate strategies for restoration of a
desirable fish population structure.
Suggested budget estimate: $100,000 for phase one.
c. Ocean/estuary research
Issue: A number of developments point to a need to learn more
about the ways in which the conditions in the ocean and estuary affect
Columbia River salmon and steelhead, the ways in which humans have changed
the estuary and nearshore ocean plume that adversely affect anadromous
fish, and what if anything we can do to restore more appropriate
conditions in the estuary and nearshore. The region has become more aware
in the last few years how much anadromous fish are affected by changes in
estuary, nearshore and ocean conditions, human and non-human induced. The
Council?s program calls for carrying capacity and evaluation work in the
estuary and nearshore. E.g., Program Section 7.1A.1. The
Independent Science Group?s Return to the River recommended
further efforts to understand the impacts of ocean, estuary and nearshore
conditions and the interaction of human management actions and ocean
conditions.
The 1996 Power Act amendment added to these concerns by calling for the
Council to consider the impact of ocean conditions on fish and wildlife
populations in making funding recommendations. The Council staff developed
an issue paper in May of this year, Consideration of Ocean Conditions
in the Columbia River Basin Fish and Wildlife Program, to assist the
Council in satisfying the new Power Act requirement. In June, the Council
adopted the recommendations in the paper as policy guidance for this
process. The paper has been attached to this document, along with a brief
discussion of how recommendations in paper are being implemented. The
paper recommends, among other things, implementing the Council?s program
by recommending one or more projects to evaluate estuary and near-shore
productivity. A key area of uncertainty directly associated with the
Council?s Power Act mandate to mitigate for the impact of the hydropower
system on salmon survival is the way the hydropower system has affected
the estuary and nearshore plume to the detriment of anadromous fish. The
Panel noted, however, that no funds have been requested for research or
other work in the estuary, nearshore or ocean, although the Panel did not
make a specific recommendation about funding.
Council recommendation: The Council recommends that an amount of
money be reserved in the FY98 budget for a research project as described
below, to study the impact of the hydroelectric development and operation
on the Columbia River estuary and nearshore plume. The proposed study
calls for a review of existing research literature and associated
analytical work, not new field work. The Council?s issue paper
identified a number of ocean, estuary and climatic programs in the Pacific
Northwest. This study is intended to capitalize to the greatest extent
possible the work going on in the programs and to be coordinated with and
not duplicate those efforts. The Council knows of no efforts to study the
impact of hydropower development and operation on the nearshore plume and
the related impacts on salmon productivity. The Council directs the
Council staff to work the ISAB and others to produce a more formal
statement of the study requested, and a competitive bid process to select
who will undertake the study.
Impact of hydroelectric development and operation on the
Columbia River estuary and nearshore plume
The amended Northwest Power Act calls on the Council to consider the
effects of the ocean in implementing the Fish and Wildlife Program. To
date, the impact of the hydroelectric system has been considered almost
solely from the perspective of direct impacts to the area above Bonneville
Dam. However, there is substantial reason to expect that the construction
and operation of the hydroelectric system has had a significant impact on
the estuary and nearshore river plume. Many actions in the Columbia River
watershed funnel down to the estuary, which becomes the recipient of
pollutants, sediments, debris and water that is produced or managed in
upriver areas. In addition, all salmon originating in upriver must pass
through the estuary as juveniles and adults. Changes in the flow regime
through the estuary and into the freshwater plume may have substantially
altered the conditions that supported salmon survival through this life
stage and thus undermined salmon survival in ways that are not well
understood.
This project would (1) provide an assessment of the importance of the
estuary to fish and wildlife recovery efforts, and (2) an analysis of the
impacts of the construction and operation of the Columbia River
hydroelectric system on the hydrology, habitats and ecology of the
Columbia River estuary and river plume and opportunities for management
action related to the estuary. It is intended to be synthesis of mostly
existing information into an assessment of the extent of impacts
especially on anadromous salmon and steelhead. No fieldwork is envisioned
in this project. It should rely heavily on existing sources of
information. However, it may be feasible to use modeling techniques to
examine the impact of, for example, flow regulation on estuarine habitats
and the river plume.
Specific objectives:
- Analyze and assess the impacts of development and operation of the
Columbia River hydroelectric system on the hydrology of the Columbia
River estuary and nearshore plume.
- Review the theories, models and empirical information pertaining to
estuary use by anadromous fish in the Columbia River.
- Examine the impacts of changes in hydrology, sediment input or other
factors caused by development and operation of the hydroelectric
system on anadromous fish life histories and on historical and
existing habitats of the estuary and plume.
- Assess the impacts of any changes in hydrology and habitat on life
history and migration patterns of salmon and steelhead in the Columbia
River.
- On the basis of this analysis, suggest management and operational
changes that might benefit the estuary and plume and recommend any
additional study needed to develop operational strategies.
- The project should be coordinated with ongoing estuary research
including the efforts of the National Marine Fisheries Service, the
National Estuary Program and the U.S. Army Corps of Engineers
(including the Corps? evaluation of the possible impacts from
proposed channel deepening).
Application: Information from this project will be used to
assess the need to modify upriver hydroelectric system operations to
enhance conditions in the estuary and nearshore ocean plume. It supplies
information pertinent to the question of carrying capacity in the estuary
and should help management of hatcheries and other actions affecting
conditions in these areas. The project should also contribute to the
assessment of losses of fish and wildlife in the Columbia River Basin
resulting from development and operation of the hydroelectric system.
Suggested budget estimate: $150,000
As noted in the study description, the results of such a study should
be relevant to the Council?s planning and funding responsibilities in a
number of ways. Two are further emphasized here: First, a review of
literature and analysis as described here would assist the Council in
determining whether this hydrosystem impact can be measured, understood
and addressed. This would allow the Council and the managers to make a
decision whether more research and planning funds should be allocated to
addressing estuary and near-shore conditions affected by the hydropower
system. Second, the information gained in this study could be immediately
useful in understanding whether the Columbia flow regime might be
re-regulated to improve estuary and nearshore conditions for anadromous
fish. Reservoir operations and flow management will be critical issues in
a Council Program amendment process. The Council will be better prepared
to address the flow issues if it has an understanding of impacts other
than just above Bonneville.
5. Mainstem actions ? evaluation of assumptions and high-cost
programs in the mainstem
a. Evaluation of migration-related
assumptions/coordination of migration-related research
Issue: The Independent Science Review Panel recognized the
emphasis placed in the Program and in regional salmon recovery efforts on
measures to improve juvenile migration through the mainstem. But the Panel
also concluded that the present level of "ecological and hydrodynamic
understanding of juvenile fish migration" is an inadequate base for
the various juvenile migration measures implemented in the basin. Thus the
Panel recommended, among other things, "quantitative evaluation of
assumptions (e.g., flow-survival) upon which structural (e.g., passage
facilities) and operational (e.g., flow augmentation) measures" are
based. (The Panel also recommended at this point that all
migration-related research, monitoring and other management activities be
coordinated and integrated, and studies to quantify food web dynamics and
other habitat conditions in mainstem reservoirs and a risk-benefit
analysis of tradeoffs required to create normative conditions and habitat
in the mainstem -- recommendations discussed above.) The Panel?s
recommendations are consistent with the mainstem hypotheses and experiment
described in Section 5.0 of the Council?s Program and in the preamble to
Section 5, as recognized by the Panel.
Council recommendation: As noted in a number of the comments,
what is known as the PATH processes is pursuing quantitative
evaluation of the assumptions upon which structural and operational
measures for juvenile migration are based. The PATH project is discussed
in more detail below. The focus in PATH has been narrow so far -- on
listed Snake River chinook and migration through the lower Snake River
dams -- but what is learned from PATH about migration assumptions should
be useful for evaluating anadromous fish migration in the lower Columbia
and elsewhere. The Council does not recommend any funding for additional
evaluations at this time.
The Council agrees with the Panel that more needs to be done to
coordinate mainstem research, monitoring and evaluation, as discussed
above. This is not an issue for a funding recommendation, however, and
should be addressed in other ways. Work did start at one time on a
coordinated research framework, an effort that stalled. The Council
recommended above that an interim coordinated research framework be
developed as part of the development of a competitive grants research
process, and that the topic be further addressed in the Council?s
upcoming Program amendment process. Central to that amendment process will
be to complete and the on-going efforts to develop a proposed integrated
framework for the Program, which is also a recommendation of the Panel.
b. Peer-review of effectiveness of high-cost
mainstem actions, in general
Issue: The Panel recommended "thorough peer-review
evaluation of the effectiveness of high-cost actions" in the
mainstem, specifically naming the smolt monitoring program, predator
control bounty and biological studies of gas supersaturation.
Council recommendation: The Council does not recommend the
creation of a separate peer review process to precede this year?s
funding recommendation for a whole range of mainstem actions. Instead, the
Council recommends a case-by-case approach to the review of specific
program areas mentioned by the Panel and others, as described in the pages
that follow -- the Council concluded that some actions would not benefit
from peer review this year, that others do need a project review during
the year that includes reference of questions to independent scientific
review, and that some programs should be reduced based on what we already
know. More general considerations of whether and how to evaluate the
high-cost mainstem actions may be a subject of a Program amendment
process.
c. Smolt monitoring
Issue: The Panel acknowledged that the smolt monitoring work
funded under the Council?s Program is of high quality. But the Panel
questioned whether the project gives insufficient attention "analyses
that try to answer critical uncertainties about various alternative
management approaches." The issue for the Council is whether it wants
to review and refine the smolt monitoring program for this year, or
whether this is something to work on over time with the managers and the
Independent Science Advisory Board, with the aim of influencing the design
of the program for future years.
Council recommendation: The Council does not recommend a review
of the smolt monitoring program this year. It provides, as the Panel
noted, high quality monitoring data that is used for in-season management.
The assumptions underlying the value of that information, and what better
information could be collected, is being or will be addressed in a number
of other ways, including through the PATH process, the reach survival
research directed by the National Marine Fisheries Service (which has
focused on the Snake, and should begin in the lower Columbia), and a
Council Program amendment process.
d. Predator control program (squawfish)
Issue: The Panel criticized the squawfish control program as
expensive "even though predation is likely the secondary end-result
of other control multiple stresses and habitat degradation." The
Panel suggested instead that "[t]he primary causes of stress . . .
might better receive both additional study and attention to
remedies." As part of its program management review, the Council
reviewed the squawfish program earlier this year, tentatively concluding
that portions of the program have merit -- certain angling methods that
are used -- but asking the managers to review and recommend more cost
effective ways to administer the program.
Council recommendation: Based on what the Council learned during
the project review earlier this year, and additional review and
considerations by staff, the Council recommends continued funding for
certain portions of the program and a cessation in funding for the rest of
the program. First, the Council recommends that what appears to be the
really effective portion of the program -- the bounty angling for
squawfish -- be funded. Bonneville and the project sponsors should
investigate whether there are more cost effective ways to pursue this
activity. Second, the less effective squawfish control activities,
including the dam angling, should not be funded. Third, the Council
concludes that this program has been so successfully monitored and
evaluated that we now have a good understanding of the predatory habits of
the squawfish, the benefits of catching which fish, and where and how to
catch them. Thus it should be possible to cut significantly the evaluation
portion of the program, funding only the basic work of monitoring the
catch and squawfish populations.
It is not yet clear to the Council precisely how the project funding
needs would be affected by these recommended changes in the program. The
Council staff should work quickly with Bonneville and the project sponsors
to develop a revised project funding estimate.
The list of projects also includes a study of predation by birds,
funded in FY97 for $119,000 and recommended in FY98 for an increase to
$280,000. The Council recommends that this project should be held pending
project sponsor review of the project with the Council.
e. Biological studies of gas supersaturation
Issue: There are four projects recommended for funding to
evaluate the effects of dissolved gas supersaturation, totaling $2.5
million. The Panel questioned whether gas supersaturation research should
receive the attention it does "even though the physical causes and
engineering solutions are known and the general biological detriment of
high gas supersaturation is well proven." The Panel concluded that
the current research effort is pursuing details "as an excuse for not
making the obviously needed engineering corrections at the dams." The
Council staff has also advised the Council that we lack a clear statement
of the information that the region still needs from the gas research --
what are the management uncertainties that affect regional decisions
involving spill and total dissolved gas, and what kind of research
information is necessary to address those needs?
A Dissolved Gas Team formed under NMFS? and the Council?s oversight
is working with a set of research needs identified by NMFS and is
developing a gas supersaturation research plan. It is unclear how the
on-going activities represented by the projects will relate to or fare
under this effort by the Dissolved Gas Team. It is not clear how the gas
research, monitoring and evaluation funded under the direct program
relates to gas research, monitoring and evaluation funded by Congress
through the Corps of Engineers.
Council recommendation: The Council recommends that the funding
for these projects be held in reserve pending the development by the
Dissolved Gas Team of a coordinated research plan for the gas
supersaturation evaluations and associated recommendations for FY98
project funding. The research plan and project recommendations are to be
reviewed by the Independent Science Advisory Board and reviewed and
approved by the Council prior to funding.
f. Law enforcement
Issue: The law enforcement program funded under the Council?s
program has been a focus of controversy for some time. The project began
in the early 1990s as a three-year demonstration or pilot project, and has
since grown into an on-going, permanent law enforcement venture that may
be the most costly single project ($4 million) in the direct program
outside of capital construction costs for new hatcheries. Questions have
been raised about the effectiveness of the program, about whether the
program is worth its high cost whatever its effectiveness, and whether its
peripheral connection to hydropower impacts and the fact that law
enforcement is a traditional activity of state, tribal and federal
governments makes it appropriate for Bonneville funding through the
Council?s program.
The Council reviewed the law enforcement program during the past year,
with an inconclusive result. An evaluation of the effectiveness of the
program is underway, with a further report due later in the year. The
Panel recommendation on peer review of high-cost mainstem actions did not
specifically mention the law enforcement program, but the accompanying
text did. The Panel noted that there is "little substantiation that
illegal catches are a major problem for salmon survival," yet the
program is "a major drain on funds needed for work to protect
juvenile salmonids."
The Columbia Basin Fish and Wildlife Authority?s proposed funding
recommendation for FY98 for the law enforcement program has been reduced
approximately $600,000 from last year?s level. It appears that the
funding reduction was not specific to any particular portion of the law
enforcement program. CBFWA?s expectation is that the Columbia Basin Law
Enforcement Council will determine the allocation later.
Council recommendation: After further review of the information
about the program, review of the comments, and public discussions, the
Council recommends that Bonneville funding for the law enforcement program
be discontinued. The Council will consider proposals to fund specific law
enforcement tasks that are tied to the core purposes of the Act, do
not present an "in lieu" issue under the Act, and are associated
with activities funded under the Program, such as protecting habitat
investments under the Program.
The Council makes this recommendation for reasons that have little do
with whether the law enforcement is "effective" or not. The main
concern is that a fish and wildlife program measure that was intended as a
pilot program, in which Bonneville money would be used as seed money to
purchase equipment and develop techniques and training for fisheries law
enforcement and public outreach, has turned into an on-going, high-cost,
permanent funding of fisheries law enforcement activities on the Columbia
River by Bonneville ratepayers. There are several reasons why Bonneville
direct program funding for law enforcement should not go beyond the pilot
program stage. The connection of the project to mitigation of hydropower
impacts is tenuous. Although the project might be classified as an
off-site hydropower mitigation activity, there appears to be an "in
lieu" issue, as Bonneville funding is being used to supplement or
replace what is a traditional function of state, tribal and federal law
enforcement.
Bonneville funding has contributed significantly by allowing the law
enforcement agencies to increase their material and technical
capabilities. In a time of tight budgets, when important mainstem actions
and research and tributary habitat and natural production activities are
not being funded, using Bonneville funding under the hydropower mitigation
obligation of the Power Act and the Council?s Fish and Wildlife Program
for law enforcement activities is at best a very low priority.
g. PATH/Bonneville non-discretionary
Issue: The Panel did not mention the PATH project in its report,
but the Council and its staff have identified this project as another
high-cost mainstem program that could benefit from closer scrutiny as to
its cost, components, direction, oversight, expectations, and relative
value. There are two issues here. The first has to do with the core work
of the PATH group. PATH is most directly linked to the National Marine
Fisheries Service?s hydropower Biological Opinion, making it a
non-discretionary ESA expense, although PATH also has its origins in the
Council Program?s mainstem hypotheses. The Council does not suggest that
PATH?s work is not of value or should be discontinued. But the cost is
relatively high (well more than $1 million), and the focus has been
correspondingly narrow so far (essentially how to understand and improve
juvenile migration survival for the listed stocks at the lower Snake River
dams), justifying scrutiny along with the other high cost mainstem
projects. A number of questions for cost and management review arise: Is
it appropriate to fund the PATH activities by essentially funding full or
part FTEs? Are there ways to control or reduce the costs, perhaps by
shifting to a "task and time accounting" system such as is used
with the Independent Science Advisory Board? Is it appropriate to fund
participation in PATH by NMFS personnel? If the main point of PATH is to
inform the federal agencies? 1999 mainstem configuration decision under
the Endangered Species Act, is there reasons to evaluate whether the work
of the group should continue at approximately $500,000 per year for a
number of years after 1999? Finally, are there ways to expand the scope of
PATH?s work to make it more relevant to the systemwide concerns of the
Council?s program, especially to extend the assessment work to the
issues in the lower Columbia?
The second issue has to do with a number of projects associated with
the PATH effort. Bonneville, in a May 9 letter to the Council, identified
eight modeling, data collection and analytical projects as
non-discretionary (totaling $1.7 million) that Bonneville labeled as
directly necessary to support the Biological Opinion and PATH activities,
or as necessary to allow Bonneville to fulfill its internal requirements
to provide river operations that support the Biological Opinion and other
Bonneville obligations. Bonneville did not explain the projects as related
to the Council?s Program. The Bonneville letter also did not make clear
how these projects are necessary under the ESA requirements and the
Biological Opinion. It is also not clear the level of importance that NMFS
puts on these projects. The Basin Authority, of which NMFS and the
agencies and tribes that participate in PATH are members, did not request
funding for some of these projects and significantly reduced funding for
others.
Council recommendation: On the first issue, concerning funding
for the core activities of PATH, the Council recommends that the funding
for PATH occur on a time-and-task accounting basis. Bonneville and the
project sponsors should review with the Council how that might affect the
funding for the project. Funding for state and tribal participation should
be held at the actual FY97 funding level ($605,000) pending the
time-and-task accounting review. The Council also requests that a thorough
cost and management review of PATH be scheduled for sometime in the year,
to address the issues noted above and others that may arise. The Council
staff should coordinate the review with NMFS, Bonneville and the PATH
participants.
On the second issue, the Council does not believe it is appropriate for
Bonneville to unilaterally label as non-discretionary a significant level
of funding for these (or any other) projects without first notifying the
Council and the agencies and tribes of an intent to declare the projects
as non-discretionary and explaining the designation. Bonneville is part of
the Bonneville fish and wildlife budget Memorandum of Agreement and the
commitments in the MOA?s Annex on budget allocation. Under the Power
Act, Bonneville is to use its fund "in a manner consistent with"
the Council?s Program; under the ESA Bonneville has concluded that it
must fund expenditures identified in the reasonable and prudent
alternative to NMFS? hydropower Biological Opinion; and under the budget
MOA, Bonneville agreed to work with the regional prioritization process to
determine how to allocate its direct fund account to these activities. The
Council recognizes that the ultimate funding decisions are Bonneville?s,
guided by the requirements of the Power Act and other laws, and that the
recommendations of the Council and the agencies and tribes are just that
-- recommendations entitled to a certain amount of consideration and
weight. Bonneville?s determinations should be preceded by a meaningful
dialogue with the Council and the agencies and tribes. The Council directs
the Council staff to work with Bonneville and the agencies and tribes to
develop a better procedure for designating non-discretionary projects in
the future.
With regard to these projects in particular, Bonneville has begun
working with Council staff to provide more information as to how these
projects are linked to Bonneville?s ESA requirements or internal needs,
and to explain how Bonneville has worked with NMFS and the PATH
participants to arrive at a coordinated understanding of what type of
modeling and analytical activities are necessary for PATH?s work and for
implementing the river operations portion of the Biological Opinion. The
Council recommends that the funding for these Bonneville?s
non-discretionary activities also occur on a time-and-task accounting
basis, and that Bonneville review the implications of that with the
Council. The Council also recommends that before the next funding cycle,
Bonneville review with the Council the work these projects fund and the
reasons for their designation as non-discretionary. Finally, the Council
will specifically request ISRP review of these projects in next year?s
project review process.
The Council withholds any recommendation on the propriety of funding
these projects, at the levels proposed by Bonneville, until it has an
opportunity to review an exchange of information and views with
Bonneville. [Option: The Council recommends that funding for these
projects be held pending Council review of the projects.]
6. Projects subject to ISAB review in FY97: Lake
Pend Oreille Fishery Recovery Project and Hatchery PIT Tagged Chinook
Study
Issue: The Council requested review by the Independent Science
Advisory Board of two study projects last year, the Lake Pend Oreille
Fisheries Recovery Project and the Hatchery PIT Tagged Chinook Study. The
ISAB responded with reports on the two projects, criticizing elements of
the study design of both and recommending revisions. The ISAB and the
Council forwarded the report on the Lake Pend Oreille project to the
project sponsor. With regard to the Hatchery PIT Tag Study, the Council
sent both the report and a letter recommending certain changes in the
study based on the ISAB?s report. It is unclear from the project
descriptions for FY98 funding or from the Basin Authority?s draft
workplan how the project sponsors for these two projects have responded to
the ISAB reviews.
Council recommendation: The Council requests that the project
sponsors explain to the Council how they have responded to the reports of
the ISAB. The Council also recommends that funding for these two projects
be held in reserve pending review by the Council of the explanations. As
guidance for future project selection processes, the Council is going to
expect that project sponsors whose projects are subject to ISAB or ISRP
review and criticism explain at the time of the next project selection
process how they have responded to the reviews.
7. White sturgeon program ? various issues
Issue: The Program activities to evaluate the status of white
sturgeon populations was the subject of a Council review earlier in the
year. The Council required nothing specific of this program at the end of
the review. Neither the Panel nor the Council staff identified fundamental
concerns with the project, but the Council staff saw the need to review
questions raised in the project review and frame funding recommendations
for the Council to consider. The key concern has been whether
implementation and possibly production activities are getting out of
sequence, ahead of what are intended at this stage to be research and
evaluation projects.
Section 10.4A of the Council?s Program calls for a series of
evaluations of the status of white sturgeon populations and of the
potential for rebuilding those populations, including evaluations of the
potential for using artificial production to supplement sturgeon
populations. Recommendations to implement production efforts or develop an
experimental white sturgeon research facility are to be submitted to the
Council for review and approval prior to implementation. The white
sturgeon project derived from Section 10.4A is actually a set of
activities in different parts of the Columbia arm of the river to study
and evaluate sturgeon populations, most combined together under the
umbrella administration of the Oregon Department of Fish and Wildlife in a
project totaling $2.16 million in the FY98 project recommendations. The
Nez Perce Tribe has a separate white sturgeon evaluation project in the
Snake basin. Finally, under Section 10.4B of the Program, Bonneville funds
a variety of activities by the Kootenai Tribe that are attempting to
restore the endangered Kootenai River white sturgeon.
Specific issues are outlined and addressed in the following Council
recommendation:
Council recommendation: Combined project/priority.
Various white sturgeon evaluation tasks in the Columbia are integrated
into one project for review and prioritization. Putting them together this
way makes it difficult to determine if all of the elements of the white
sturgeon effort are equally effective and warrant funding and whether all
of the ranking criteria and scoring apply equally to all elements, making
them of equal priority. A response has been that the Council?s Program
calls for these tasks to be integrated, that administrative efficiencies
are gained by combining them together and that other projects in the fish
and wildlife program also bring together various activities and project
sponsors. This last point is true, but few if any projects link together
disparate activities spread out over such a large geographical area as the
white sturgeon project. The Council recommends that during the FY99
project review process that the information about the project be presented
so that the ISRP will be able to review the component parts of the white
sturgeon project.
Evaluation/implementation/artificial production. Questions have
been raised as to whether statements of work for this project indicate
funding is being sought for implementation of restoration measures
involving production that have not yet been reviewed with the Council. For
example, project sponsors apparently have concluded that experimental
transplants of wild fish from below Bonneville into The Dalles reservoir
have been a success, and they would like to explore the use of
supplementation into reservoirs. The Council recommends that any proposed
white sturgeon supplementation activities need to be treated as are the
other production activities in the basin, that is, as candidates for
inclusion in the comprehensive review of artificial production and as
subject to the interim approach for reviewing hatchery investments
described above. Supplementation and aquaculture activities should not
expand without Council review. The Council requests that the project
sponsors develop for Council review an explanation as to how they expect
the white sturgeon production initiatives to move through the Council?s
production review process. Bonneville should not allocate funding for
implementation until the proposed implementation measures and the
evaluation work they are based on are submitted to the Council for public
review.
Kootenai River white sturgeon program. This is an entirely
separate project based in Section 10.4B of the Council?s Program, which
funds a number of activities that are attempting to restore the endangered
Kootenai white sturgeon. The production portion of this program will need
to be evaluated as part of the comprehensive review of production. In
addition, the production activities have had operational problems that may
indicate the need for project review or for more support. FY98 funding for
the project should continue, but the Council requests the project sponsors
review with the Council immediately the management and funding needs of
the project.
8. Wildlife
The Panel made a number of recommendations regarding the Wildlife
portion of the Council?s Program, most of which are addressed in the
explanations in response to the Panel?s recommendations that follow the
specific project descriptions. Two key or programmatic issues require
attention here:
a. Monitoring and evaluation ?extend to include
some population monitoring
Issue: In evaluating the wildlife section of the Program, the
Panel concluded that use of the Habitat Evaluation Procedure (HEP) for
determining wildlife losses was reasonable and appropriate for
quantification of the value of potential projects, and that the decision
to mitigate at the level of habitat was prudent. However, the Panel
pointed out that one drawback of HEP is that it does not capture wildlife
population dynamics directly. The Panel recommended that monitoring and
evaluation be extended to include a requirement for some degree of direct
monitoring of wildlife populations.
Council recommendation: The Council agrees that HEP has a
weakness with regard to landscape level changes and population dynamics.
The Columbia Basin Fish and Wildlife Authority has recommended continued
funding for the development of a regional monitoring and evaluation
process for wildlife mitigation projects, consistent with the Draft
Wildlife Plan (Appendix G of the Council?s Fish and Wildlife Program). [
The Draft Wildlife Plan has remained a draft while Bonneville has been
completing an Environmental Impact Statement on its funding of wildlife
mitigation projects. Bonneville completed the EIS this summer. The Council
will act soon to finalize the Wildlife Plan. Nothing in the EIS, or in the
Panel?s report, has undermined the fundamental principles and approach
of the Draft Wildlife Plan. In fact the Panel?s recommendations are
largely consistent with and an endorsement of what is in the Wildlife
Plan.] The Draft Plan explicitly recognizes the need to include some level
of population monitoring as part of the procedure. The Council recommends
that the development of this monitoring and evaluation process continue,
and that its development be coordinated with the Panel.
b. Acquisition of land and land easements
Issue: The Panel recommended that acquisition of land and land
easements continue to be given a high priority in the Wildlife Program.
Council recommendation: The Council agrees with this
recommendation and believes that it is consistent with the Council?s
Wildlife Program goals and criteria. The Council also concludes that the
wildlife projects recommended by the Columbia Basin Fish and Wildlife
Authority are consistent with this recommendation, with nearly 90% of the
recommended funding being directed toward easement and acquisition
projects.
9. Information for the project selection process/coordinated
information service
a. Project selection process and information
Issue: The Panel faulted the Council and other participants in
the project selection process for the quality of information generated for
the project review process, in terms of both (a) the information about the
projects themselves and evaluations of those projects, and (b) the lack,
in their view, of a systematic inventory of what has been done and not
done to implement the Council?s program. The Panel?s recommendations
include improvements in the project information format, development of
uniform standards and policies on project review, annual project
evaluations and detailed peer review of on-going projects every three to
five years, a "more information-rich accounting and reporting
system," the funding of the comprehensive management review called
for in Section 3.1E of the program, and more.
Council recommendation: The Council directs its staff to explore
with the Panel and with Bonneville and other participants what is
currently being done in the way of obtaining information about the
projects and the Program and what reforms should be made before next year?s
project selection process begins. The Council expects an update report
before the beginning of the FY99 project selection process. See also the
explanations in the document that directly respond to each recommendation
of the Panel.
b. Coordinated regionwide information service
Issue: A coordinated, regionwide Internet-based information
service to collect, organize and post research findings, policy statements
and other documents regarding Northwest fish and wildlife recovery actions
would be useful to implementers of the Council?s Fish and Wildlife
Program and other recovery efforts. However, the scope and potential for
such a service is not clear at this time.
Council recommendation: The Council recommends that any decision
to fund such a service be deferred, while the Council, Bonneville and the
Columbia Basin Fish and Wildlife Authority form a team to assess current
information sources, identify information needs, develop a proposal for a
coordinated system to meet those needs, including a proposal for how to
select the contractor to develop and maintain the system. This team should
be formed no later than October 1, 1997, with a report from the team
within one month. Until this assessment is completed, the Council
recommends that not more than $90,000 be reserved in the FY98 budget for
this purpose, as determined by Bonneville?s current allowance for a
similar service. The Council will make a recommendation about whether and
how to spend that reserved amount after reviewing the assessment.
^ top
|