Review of administrator's actions
839b(i). Review
The Council may from time to time review the actions of the Administrator
pursuant to this section and section 839d of this title to determine whether
such actions are consistent with the plan and programs, the extent to which
the plan and programs is being implemented, and to assist the Council in
preparing amendments to the plan and programs. [Northwest Power Act, §4(i),
94 Stat. 2711.]
839b(j). Requests by Council for action
839b(j)(1). The Council may request the Administrator
to take an action under section 839d of this title to carry out the
Administrator's responsibilities under the plan. [Northwest Power Act,
§4(j)(1), 94 Stat. 2711.]
839b(j)(2). To the greatest extent practicable within
ninety days after the Council's request, the Administrator shall respond to
the Council in writing specifying--
839b(j)(2)(A). the means by which the Administrator
will undertake the action or any modification thereof requested by the
Council, or [Northwest Power Act, §4(j)(2)(A), 94 Stat. 2711.]
839b(j)(2)(B). the reasons why such action would not
be consistent with the plan, or with the Administrator's legal obligations
under this chapter, or other provisions of law, which the Administrator
shall specifically identify. [Northwest Power Act, §4(j)(2)(B), 94 Stat.
2711.]
839b(j)(3). If the Administrator determines not to
undertake the requested action, the Council, within sixty days after notice
of the Administrator's determination, may request the Administrator to hold
an informal hearing and make a final decision. [Northwest Power Act,
§4(j)(3), 94 Stat. 2711.]
839b(k). Review and analysis of 5-year period of Council
activities
839b(k)(1). Not later than October 1, 1987, or six
years after the Council is established under this chapter, whichever is
later, the Council shall complete a thorough analysis of conservation
measures and conservation resources implemented pursuant to this chapter
during the five-year period beginning on the date the Council is established
under this chapter to determine if such measures or resources:
839b(k)(1)(A). have resulted or are likely to result
in costs to consumers in the region greater than the costs of additional
generating resources or additional fuel which the Council determines would
be necessary in the absence of such measures or resources; [Northwest Power
Act, §4(k)(1)(A), 94 Stat. 2711-2.]
839b(k)(1)(B). have not been or are likely not to be
generally equitable to all consumers in the region; or [Northwest Power Act,
§4(k)(1)(B), 94 Stat. 2712.]
839b(k)(1)(C). have impaired or are likely to impair
the ability of the Administrator to carry out his obligations under this
chapter and other laws, consistent with sound business practices. [Northwest
Power Act, §4(k)(1)(C), 94 Stat. 2712.]
839b(k)(2). The Administrator may determine that
section 839a(4)(D) of this title shall not apply to any proposed
conservation measure or resource if the Administrator finds after receipt of
such analysis from the Council that such measure or resource would have any
result or effect described in subparagraph (A), (B) or (C) of paragraph (1).
[Northwest Power Act, §4(k)(2), 94 Stat. 2712.]
^ top |