|
|
|
Studies to test changes in spill and reservoir operations in 2004
Over the past several weeks a workgroup of action agencies, NOAA, fish
and wildlife managers and Council staff have held technical discussions on
the feasibility of implementing 2004 summer spill and reservoir tests
called for in the Council's mainstem amendments. Issues discussed during
these work sessions have included such things as test design, study
logistics, performance measures, levels of precision and study costs. Thus
far, discussions have focused primarily on summer spill tests in the lower
river. Discussions on studies to evaluate changes in reservoir operations
are continuing and will be expanded in the coming weeks. This memo
attempts to briefly summarize what has been considered and currently
concluded regarding possible 2004 summer spill and reservoir studies.
Summer spill tests
Currently there are five summer spill test options being considered.
General spill levels and proposed studies for the options are summarized
in the table below:
|
Option
|
Spill Level |
Studies Proposed |
| 1 |
Current summer spill (status quo) |
Current planned project-level spill studies. No additional
studies
|
| 2A |
Reduced summer spill |
Maintain planned spill studies.
|
| 2B |
Reduced summer spill |
Modify planned spill studies. Perform additional summer spill
studies/monitoring
|
| 3 |
Current summer spill status quo) |
Maintain planned spill studies plus perform additional
system-level summer spill/transport studies/monitoring
|
| 4 |
Additional summer spill |
Discontinue planned spill studies. Perform additional summer
spill/transport studies/monitoring
|
The workgroup has come to the following conclusions:
- A major constraint in conducting summer spill studies is the
difficulty of tagging fish later in the season. Warmer water
temperatures increase stress on fish that are handled and tagged so
tagging fish after early July increases mortality risk and sample
bias. Also, as the season progresses fewer and fewer fall chinook
juveniles are found in the river making it more difficult to capture
sufficient numbers of fish. Summer studies that require handling and
tagging juveniles usually ends about July 20 of each year. Thus for
2004 it was assumed that no summer spill studies can be conducted in
August.
- Proposed studies for Option 4 have not been submitted. How this
option will be evaluated must be determined at a later time. For
Option 3, two types of survival studies were considered for 2004
summer spill tests-- 1) systemwide studies and 2) project specific
studies (as currently planned for options 1 and 2). Systemwide studies
attempt to estimate juvenile survival through the entire hydrosystem
or a particular stretch of hydroprojects. Project specific studies
attempt to estimate survival past an individual hydroproject.
- After lengthy discussions and analysis it was established that a
systemwide survival study is probably not feasible in 2004. To
meet the needed statistical confidence limits, a systemwide study
would require many years of study and millions of tagged fish. On the
other hand, project specific studies using radio tags are probably
doable and could provide project specific survival information.
- While doable, project specific studies carry uncertainties. These
uncertainties include: 1) whether or not there are indirect or delayed
effects on fish passing through the hydrosystem; 2) whether or not
July survivals can fairly represent August survival; 3) whether or not
the juvenile sampling bias is significant (radio tags need larger
fish); 4) whether or not project specific survivals can reasonably
estimate system survival; 5) whether or not radio tags affect fish
survival.
- The Corps of Engineers is developing a scoping document to help
clarify the assumptions and uncertainties surrounding project specific
studies. The scoping document will be soon submitted to and considered
in the regional technical forum process.
What this means for possible 2004 summer spill tests
- Under Option 1, the status quo, summer spill studies in 2004 are
planned for Ice Harbor, The Dalles and Bonneville dams. These are
project specific studies evaluating survival past an individual
project.
- Based on the proposed alternatives and study constraints outlined
above, a project survival study at Bonneville Dam under Option 2B is
the only other study that can be reasonably implemented in 2004. This
is a modified project survival study from the one that is currently
being proposed at Bonneville.
- For Option 2A and Option 3 no additional studies to the status quo
would be implemented in 2004. Again, study plans have not been
submitted for Option 4.
- An alternative to conducting new spill studies could be to update
existing passage survival models with the most current project
survival information and proceed with the planned 2004 spill studies.
Once new survival information becomes available it would also be
incorporated into the models. Any change in spill from Bi-Op
operations in summer 2004 could be evaluated using models to estimate
the effects of the operation on juvenile survival. This could be done
with both Option 2A and Option 2B.
- In order to implement new studies in 2004, tags must be ordered by
early January 2004. A decision must be made soon as to whether or not
new spill studies will be undertaken so studies can be developed and
tags ordered.
- The approximate cost for each new project survival study would be
approximately $2 to $3 million.
- How the tests will be funded should be clarified.
Reservoir Operation Studies
Montana Fish, Wildlife and Parks (MFWP) believes that an evaluation of
the biological effects of a modified summer draft at Libby and Hungry
Horse can be conducted in 2004. Studies to evaluate the effects of changes
in reservoir operations on resident are well developed. In general, MFWP
proposes to study resident fish populations above and below Libby and
Hungry Horse dams by collecting needed physical and biological information
and utilizing reservoir and riverine habitat modeling techniques. A
proposal to assess biological and physical responses to a modified summer
draft has been submitted to the workgroups for consideration. The
CBFWA resident fish committee is preparing to review the proposal.
Likewise, Council staff is working with MFWP to facilitate a review of the
proposal by the ISRP.
While upriver studies are fairly well developed, lower river
evaluations for a modified summer draft operation have only been briefly
discussed. There are several problems with attempting to determine the
affects of flow changes on outmigrating fall chinook and it is unclear how
these problems will be overcome:
- A system-wide study to estimate changes in survival is probably not
feasible.
- The proposed flow changes are so small relative to the total river
flow any change in survival may not be measurable.
- If both summer spill and reservoir operations were modified in 2004
it would not be possible to separate the survival effects of each
operation.
Related link: Oregonian
article
^ top
|
|