The Columbia River Treaty (full text) between the United States and Canada mandated the construction and operation of three water-storage dams in British Columbia (Canadian storage) for the purpose of providing flood control and optimum hydropower generation in the Columbia River Basin in Canada and/or the United States. The Treaty also authorized construction of Libby Dam on the Kootenai River in Montana for flood control and other purposes in the United States. All four dams were built.

By utilizing water storage sites in the upper Columbia River Basin that allowed for manipulation of the natural flows, the Treaty brought more surety and increased hydropower generation at dams downriver and also provided flood control. The Treaty was signed in January 1961 and implemented on September 16, 1964. Importantly, the Treaty considered that the value of flood control and hydropower dwarfed the value of other costs and benefits, and so it made no explicit provision for other values such as water-flow benefits for salmon and steelhead. By the time the treaty became law, salmon and steelhead had been extinct in the upper Columbia River for more than 20 years because of Grand Coulee Dam, which has no fish passage facilities for either juvenile or adult fish.

The treaty is implemented by entities, one for the United States and one for Canada. In a 1963 agreement, the government of Canada designated the Province of British Columbia to implement the treaty. BC Hydro, the provincial power-marketing corporation, is the Canadian entity under the treaty. For the United States, the administrator of the Bonneville Power Administration and the Northwestern Division Engineer of the U.S. Army Corps of Engineers comprise the entity.

The treaty has no expiration date. It will continue indefinitely unless one country requests termination, which is allowed anytime after 2024, 60 years after its ratification, given at least 10 years advance notice (no later than 2014).

In the treaty preamble, the two countries state that construction of three dams in British Columbia — Duncan on the Duncan River, a tributary to Kootenay Lake, and Keenleyside and Mica, both on the mainstem Columbia River — would provide benefits to the two countries in the form of additional hydroelectricity and flood control “. . . in a manner that will make the largest contribution to the economic progress of both countries and to the welfare of their peoples of which those resources are capable.”  The preamble noted that the people of the United States and Canada “have, for many generations, lived together and cooperated with one another in many aspects of their national enterprises for the greater wealth and happiness of their respective nations.”  The Treaty was seen as a natural evolution of that cooperation.

In recognition of this long friendship and in order to take advantage of their shared river for economic gain, the countries agreed that Canada would provide 15.5 million acre-feet of water storage:  7 million acre-feet at Mica Dam, 7.1 million acre-feet at Keenleyside and 1.4 million acre-feet at Duncan. The Treaty also authorized the United States government to build Libby Dam, and Canada agreed that the reservoir, Lake Koocanusa (an acronym:  Kootenai, Canada, USA), could back 42 miles into British Columbia.

To realize the downstream power benefit, the United States (Article III, Paragraph 1) . . . shall maintain and operate the hydro-electric facilities included in the base system and any additional hydro-electric facilities constructed on the main stem of the Columbia River in the United States of America in a manner that makes the most effective use of the improvement in stream flow resulting from operation of the Canadian storage for hydro-electric power generation in the United States of America power system. The United States can discharge the “most-effective-use” obligation by reflecting the requirement in the studies that determine the downstream benefit. Importantly, Canada has to operate in accordance with agreed operating plans. In the absence of specific agreement, these plans are designed for flood control and to produce optimum hydroelectricity and not directly for other purposes such as providing water for irrigation, navigation, or flows to assist salmon and steelhead migration in the lower Columbia River.

Under the Treaty, the estimated additional usable hydropower generated in the United States compared to the 1961 United States reservoir system — the downstream power benefit — is shared equally by the two countries. Comparison to the 1961 system gives Canada a “first added” benefit. This, along with other limits, keeps the benefit calculation higher than the actual marginal benefit, which is significantly reduced due to the addition of reservoirs in the United States after 1961, such as those behind Libby and Dworshak dams (Dworshak is on the North Fork Clearwater River in Idaho).

Canada’s share of the downstream power benefit calculation is called the “Canadian Entitlement.”  The original Canadian Entitlement, following completion of the dams, was 1,377 megawatts of capacity (half of the total additional dependable generating capability at the United States dams) and 759 average-megawatts of electrical energy (this means 759 average megawatts delivered at rates up to a maximum of 1,377 megawatts for a period of a year). The countries anticipated these amounts would decline over time. This is because it was assumed that 1) increasing demand for power would be met with new thermal-fuel power plants – coal, natural gas, nuclear — for baseload generation, and 2) the dams increasingly would be used to supply extra energy — peaking power — when needed.

In fact, new power plants were added, or planned for addition, to the Columbia River hydropower system through the Hydro-Thermal Power Program, but not as much new baseload thermal generation as the Treaty anticipated. Thus, today we rely more on the dams than the Treaty planners expected. During August 2007 through July 2008, the Canadian Entitlement was 1,241 megawatts of capacity and 482.8 average-megawatts of energy. This energy amount was enough for about 280,000 average electrically heated homes.

Whether the Entitlement is 759 or 482.8 average-megawatts, it is a lot of electricity then and now. In 1964, the Province of British Columbia didn’t need it and wasn’t anticipating needing it for 30 years because the province was constructing a large dam on the Peace River in the northeastern part of the province. So the province sold the Canadian Entitlement to a consortium of utilities in the United States, organized as the Columbia Storage Power Exchange (CSPE), for 30 years for a lump sum of $253.93 million in U.S. dollars (adjusted from $254.4 million for early payment). This was considered a “pre-sale” of the benefits for that purpose, as it was assumed the benefits would continue to flow as long as the Treaty was in force. This “pre-sale” plus payments for flood control paid for a large portion of the construction of Mica, Keenleyside, and Duncan dams.

Duncan Dam, at the northern end of Kootenay Lake, was completed in 1967; Keenleyside Dam, just north of Castlegar, was completed in 1968; and Mica Dam, about 80 miles north of Revelstoke, began storing water in 1973 and generating power in 1976. Libby Dam on the Kootenai River in Montana began operation in 1972 and was completed in 1975. The Canadian Entitlement benefits do not include the effect of Libby Dam operations, but the province expected to acquire more than 200 average-megawatts of power benefits downstream in Canada from Libby operations. On the basis of the anticipated additional stream-flow regulation, and the expected increased power benefits, BC Hydro built its Kootenay Canal plant on the Kootenay River just downstream of Nelson at ratepayer expense.

The 1964 pre-sale of Canadian downstream benefits expired in phases 30 years after the scheduled completion of each Canadian dam. With the expiration of the pre-sale deal, Canada became entitled to receive actual power, as opposed to the “pre-sale” cash equivalent. In April 1998, the United States and Canada agreed on new terms for the continued return of the Canadian Entitlement. The 1998 agreement called for power to be returned to British Columbia in phases at locations other than the Treaty-stipulated location of Oliver, British Columbia, a small town on the Okanagan River at the border. That was originally a convenient point between the eastern and western extremes of the basin, but it was not where the province wanted the power, then or in 1998, and would have required the United States to build new transmission to deliver it. Also, the 1998 agreement allowed BC Hydro to market its share of the energy in the United States, if it chose to, rather than accepting delivery in British Columbia. Today the energy is delivered to British Columbia over two 500,000-volt lines at Blaine, Washington, south of Vancouver, and a 230,000-volt line at Nelway, Idaho, north of Sandpoint.

Treaty History and Politics

The idea for the Columbia River Treaty of 1964 dates to 20 years earlier when, in March 1944, the United States and Canada asked the International Joint Commission (IJC) to investigate “... whether a greater use than is now being made of the waters of the Columbia River System would be feasible and advantageous.”  The IJC took 15 years — until April 1959 — to complete its report.

The report discussed the potential benefits of hydropower development in the Canadian Columbia River Basin and how the benefits might be apportioned. Nine diplomatic negotiating sessions, the first one in February 1960, followed. The Treaty was completed and signed in January 1961 and ratified by the two countries three years later.

While the treaty authorized an equal sharing of the additional hydropower generation that results from additional water storage and coordinated water releases, the impacts of the dams were not equally shared by the two countries. The dams flooded fertile river valleys in British Columbia where the population was concentrated. More than 2,000 people, hundreds of farms, and 13 communities were displaced. In addition, Libby Dam flooded productive agricultural land in both countries. Operation of the treaty dams caused yo-yo water level fluctuations in the Kootenay(i) and Columbia rivers, which led to bank erosion problems.

The treaty gave the United States large amounts of power and flood control benefits from the operation of Canadian dams and Libby, plus small amounts of recreation and fishery benefits, adverse impacts on other fish, and loss of land upstream of Libby. British Columbia got three dams, large power benefits from the treaty dams and at Canadian dams downstream of Libby; flood control downstream; beneficial and adverse impacts to recreation, navigation, and fish; major flooding and dislocation of whole communities; and one-half of the estimated power and flood-control benefits created downstream in the United States. (The province took its share of the U.S. flood control benefits for the first 60 years in up-front cash payments, and took a one-time cash payment for the additional hydropower benefits for the first 30-years. These funds were used to build Duncan and Keenleyside dams and partially fund construction of Mica Dam.

Construction of the Treaty dams was the second major power development in the United States to impact the people and environment of southeastern British Columbia. First, the completion of Grand Coulee Dam in 1941 eliminated salmon runs from the mainstem Columbia River and its tributaries in British Columbia; 20 years later whole towns were relocated for the benefit of power generation and flood control in Canada and the United States. Unlike Grand Coulee Dam, however, which the Canadian federal government did not protest, this time Canada got something in return — a 50-percent share of the additional power and flood-control benefits that Canadian storage operations created in the United States (Canada’s share of the United States flood control benefit was calculated at $64.4 million; this was paid by the United States when the projects began operating, with small increments being paid later for early completion of Duncan and Keenleyside). This was an important concession by the Americans, whose official position in the initial treaty negotiations had been that Canada deserved a monetary settlement for the inconvenience of storing water and displacing its people, but not an actual share of the downstream benefit. In fact, the downstream benefit was the quid-pro-quo to Canada, according to Professor Nigel Bankes of the University of Calgary Law School, who has written extensively about the Treaty.

Tim Newton, an expert on the Treaty who retired from PowerEx, the power marketing subsidiary of B.C. Hydro, observes that while the governments of British Columbia and Canada shared a vision of increased water storage, more hydropower, and industrial development in British Columbia, it was a vision often clouded by shorter-term goals. Electric utilities and government agencies in both countries recognized the potential of the Columbia River to provide the desired storage and power, but the IJC was taking its time on its investigation, and cross-border water-storage discussions in the late 1940s and early 1950s seemed to be going slowly as well.

“With a change of government in British Columbia, Kaiser Aluminum proposed building a ‘low’ dam on the Arrow Lakes, at Kaiser’s expense, and Kaiser would provide the province with 20 percent to 30 percent of the downstream benefits. This was too tempting for the new government, and they signed a memorandum of understanding with Kaiser in September 1954,” Newton said. “The provincial opposition parties used this agreement as a political issue, and the Canadian federal government joined them in opposing this plan on the grounds that it would not allow full development of the Canadian watershed, although it was partly to strengthen the federal role in negotiating the anticipated treaty.”

The “low” Arrow Lakes dam was expected to cost $30 million, but the deal lapsed when the Canadian Parliament approved Bill No. 3, the “International Rivers Improvement Act,” the same year. Bill No. 3 required a federal license for any project in Canada that altered the flow on a river that crosses the international border. The federal government made it clear it would not approve a license for the Arrow Lakes dam.

“At this point in time, the [Canadian and American] federal objective was to keep the IJC process on track,” Newton said. “A lot of the discussion related to the loss of the Canadian competitive position that would result if the ownership of major natural resources was given to ‘foreign’ entities. Another major federal objective was to convince the U.S. that returning 50 percent of the downstream benefits would be better for the U.S. than having Canada divert water out of the Columbia Basin.”

Nonetheless, both countries remained interested in building dams in the Canadian headwaters in order to boost power generation downstream — and also in British Columbia. In 1955, the Puget Sound Utilities Council proposed Mica Dam to provide 1,400 megawatts of power for British Columbia and 1,800 for the United States. The same year, the Canadian Parliament conducted hearings on power developments in the upper Columbia Basin, including diverting the Kootenay and Columbia in ways that would increase power generation. As part of the federal strategy the Canadian Section of the International Joint Commission, for example, proposed to divert 15 million acre-feet at Revelstoke — about 67 percent of the river’s flow at that point — through a mountain tunnel into the Fraser River for exclusively Canadian hydropower purposes. It ultimately didn’t happen, but the political climate in both countries in the 1950s supported dam-building in the Columbia and Fraser basins. Partly to assist the IJC study, Canada ordered seven engineering studies of possible dam sites between 1956 and 1961. Meanwhile, in spite of very close cooperation at the technical level, political suspicions continued between the Canadian federal government and the British Columbia provincial government.

“During the negotiating period, the two levels of government managed to keep a unified approach, but even during this period there was a fundamental misunderstanding,” Newton said. “The province wanted to develop both the Peace and Columbia rivers at the same time and was very public about this ‘two-river policy.’  The federal government was sure that this was a negotiating position with respect to the U.S., and also was sure that the Peace River development would be abandoned once the Treaty was signed. So the federal government believed it was negotiating for benefits that would be used in Canada immediately. This misunderstanding contributed to the delay in Canadian ratification of the Treaty.”

Both countries supported a diplomatic process to decide on Columbia River power developments, and the result was the completion of the Columbia River Treaty, signed by President Dwight Eisenhower and Prime Minister John Diefenbaker in January 1961, and approved by the United States Senate in March. Once the Treaty was signed, British Columbia opened negotiations with the Canadian federal government so that it could implement its policy of power developments in both the Peace and Columbia rivers. To ratify the treaty it had signed, the federal government had to set aside its differences with the province and help sell the downstream benefits of the additional Canadian storage to the United States. At the same time, the federal government changed in Canada.

Negotiating the sale of the downstream benefits, which required a Treaty protocol between the United States and Canada and agreements between Canada and British Columbia, took several years. A key issue was the question of who would pay to build the Canadian dams. Ultimately, the two countries accepted a proposal by the province’s pro-development premier, William Andrew Cecil Bennett. Bennett proposed that because the power was not needed in British Columbia, the downstream power benefits could be sold to an entity in the United States for 30 years in a lump sum, and that this one-time payment could be used to pay for building the dams. This was an acceptable offer to utilities in the Pacific Northwest, and the three mid-Columbia public utilities in Washington — Grant, Chelan and Douglas — led the effort to create the Columbia Storage Power Exchange (CSPE) in May 1964. The agreement among the CSPE utilities was that half of the Canadian Entitlement would go to four private utilities and the other half to 37 public utilities, all in the Pacific Northwest service territory of the federal Bonneville Power Administration.

Because the Canadian Entitlement power was not needed in the Pacific Northwest until the 1980s, Bonneville helped the CSPE owners sell the Canadian Entitlement power in the early years to California utilities. First, the power was to be delivered over new high-voltage transmission lines — the Pacific Northwest/Pacific Southwest Intertie, whose construction depended on the successful completion of the Treaty (interestingly, the Treaty thus became dependent on completion of the Intertie). Second, Bonneville led the creation of a Pacific Northwest Coordination Agreement that assured owners of projects downstream of Canadian storage that major American reservoirs would be operated optimally with exchanges of power between utilities, as needed to create the expected Treaty power benefits. Third, the CSPE exchanged its rights to the Canadian Entitlement with Bonneville in return for a guaranteed amount of firm power to be delivered from Bonneville to the CSPE. This eliminated the uncertainty of selling an unknown amount from future Entitlement calculations and allowed the CSPE to obtain a lower interest rate for the sale of CSPE bonds. To raise cash to build the Canadian dams, the CSPE issued $314.1 million in revenue bonds and, after setting aside an amount to pay interest during the nine-year construction period for the dams, delivered $253.93 million, the negotiated amount of the Canadian Entitlement, to BC Hydro to build the dams.

It was the deal W.A.C. Bennett wanted, and it was a deal the U.S. could accept, but it wasn’t the deal many people in British Columbia wanted. For example, historian Geoffrey Molyneaux wrote that the “hardware merchant from Kelowna” (Bennett) outplayed Prime Minister John Diefenbaker and Justice Minister Davie Fulton. Molyneaux wrote that the Canadian federal government mishandled the three-way Columbia power negotiations with the United States and the province. Bennett got what he wanted; his critics claimed that the Americans did, too.

There were Treaty critics in the United States, as well. Dr. John Krutilla, who wrote extensively about the Treaty economics in the 1960s, thought there were better alternatives for the United States and Canada. But the consensus of most U.S. government and utility officials at the time was that although the Treaty was not the best deal for the United States, it was good enough.

From Treaty to Trust

Professor Nigel Bankes of the University of Calgary says that at the time the Treaty was signed and the dams were built, people living along the upper Kootenay River and along the Arrow Lakes saw themselves as people in the way. They knew they would suffer losses, they knew others would benefit, and they knew that all sectors of their local economies would suffer from the creation of reservoirs and their periodic fluctuations of elevation. Bankes says that in addition to the losses sustained by individuals, and the loss of historic community identities, the agricultural, mining, forestry, and fishery sectors of the economy all suffered serious and permanent setbacks. Some 231 square miles of valley bottom land was flooded. Despite the bright promise of the Treaty, for decades after ratification the benefits were realized far from the areas affected by dam construction. For some 2,300 residents of southeastern British Columbia, this was anything but the greater wealth and happiness promised in the Treaty.

That began to change in 1995 as the province anticipated the end of the 30-year, one-time payment for the Canadian Entitlement. Soon power would begin flowing to British Columbia from the United States, and the province wanted to be ready with a plan for spending the new money that power would create. Appropriately, the province’s Legislative Assembly favored investing the downstream power benefit in the areas most affected by the Treaty dam construction. Following a year of public meetings to gather ideas on how to mitigate the impacts of the Treaty, in 1995 the Legislative Assembly approved the Columbia Basin Trust Act, which created the Columbia Basin Trust. The Trust, governed by a board of directors comprising residents of the affected areas, is empowered to spend a portion of British Columbia’s share of the additional hydropower income to mitigate the social, economic, and environmental impacts of the Treaty dam construction. The amount of funding available is made possible by the sale of the Canadian Entitlement but is not dependent on the magnitude of the Entitlement or the price for which it is sold. Since its inception, the Trust has invested in social and educational programs, fish and wildlife habitat improvements, development of small businesses, and tourism-related economic developments including major investments in golf and ski resorts.

The Trust also is involved in hydropower development. Columbia Power Corporation, which is owned by the province, has a primary mandate to undertake power-project investments as the agent of the province on a joint-venture basis with the Trust. Columbia Power and the Trust formed the Power Project Joint Venture to assess and advance power projects. Each owns half of the joint venture, with Columbia Power as the manager. When a decision is made to build a new power plant or expand an existing one, a separate, jointly owned company is created for that purpose.

The first of these joint-venture projects was the 187-megawatt power plant at Keenleyside Dam, which began generating power in 2001. The facility, known as the Arrow Lakes Generating Station, is owned by Arrow Lakes Power Corporation, which is jointly owned by Columbia Power and CBT Arrow Lakes Power Development Corporation, a subsidiary of the Trust. The hydropower income is split between Columbia Power and the province.

Columbia Power completed a 120-megawatt expansion at Brilliant Dam on the Kootenay River at Castlegar in 2007. Brilliant Dam and its existing 145-megawtt power plant were purchased in 1996 by Brilliant Power Corporation, which is owned by Columbia Power and CBT Power Corporation, another subsidiary of the Trust. Up to 90 percent of the electricity generated at the new powerhouse is sold to BC Hydro under two long-term contracts.

Columbia Power also owns rights to build a second powerhouse at Waneta Dam at the mouth of the Pend Oreille River just north of the international border. The existing dam and powerhouse are owned by Teck Cominco Metals Ltd. Waneta Expansion Power Corporation, a company created jointly by the Trust and Columbia Power, is planning a powerhouse with a capacity up to 435 megawatts. In October 2010, Columbia Power Corporation and the Columbia Basin Trust announced they had signed a partnership agreement with Fortis, Inc., to construct the Waneta expansion powerplant. Under the agreement, Fortis has a 51-per cent share of the project, Columbia Power Corp. will own 32.5 per cent, the Columbia Basin Trust will own 16.5 per cent.

Treaty future

While the Treaty has no specified end date, either country can terminate most of the provisions as early as September 2024 with a minimum 10 years’ written notice. Under the treaty, the assured annual flood control procedures will end in 2024, whether or not the treaty is terminated, replaced by on-call flood control, in which the U.S. would ask Canada to store water after using available flood control space in U.S. reservoirs.

According to the U.S. and Canadian entities, if the Treaty continues, after 2024 coordinated annual planning of optimum U.S. and Canadian hydropower operations continues, the U.S. will continue to pay Canada its entitlement, and there would be certainty in Canadian water-storage operations though Treaty planning and coordination. If the Treaty is terminated, BC Hydro would operate Mica, Keenleyside, and Duncan dams for Canadian power benefits, except for called-upon flood control and subject to river-level limits at the international border required by the 1909 Boundary Waters Treaty, and the two countries would continue to coordinate Libby Dam operations. The Canadian Entitlement would end.

In order to prepare a recommendation to the federal governments, the U.S. and Canadian entities conducted a series of studies to provide fundamental information about post-2024 conditions, with and without the Treaty. The studies were released for public review in July 2010 and are posted on the entities’ website. These initial studies only addressed power and flood control. According to the entities, this narrow scope was necessary to allow an informed regional discussion regarding how to model other factors such as fisheries mitigation and additional irrigation withdrawals on top of the existing baseline operations. Here are some of the findings of the Phase 1 studies:

  • Canadian Entitlement energy would decline over time from the current (2010) 536 average megawatts to 470 average megawatts in 2025 and about 290 average megawatts by 2040 (290 average megawatts is enough electricity to power approximately 147,000 Northwest homes for one year; 536 average megawatts is enough for about 271,000 homes). The Entitlement capacity would increase from the current 1,316 megawatts to 1,525 megawatts by 2045.
  • Without the Treaty, average annual energy production in Canada and the U.S. remained essentially unchanged, but the monthly shape of energy production varied from the coordinated operation if the treaty continues.
  • Without the Treaty the ability of the U.S. hydropower system to meet firm loads within the critical period (critical water-storage sequence) diminished by approximately 225 average megawatts. In addition, the critical period was shortened from four years to one, which may be of concern during prolonged low-inflow conditions.
  • Without the Treaty, the number of times the U.S. would invoke the called-upon flood control in Canada depends on what level of flood-control protection, or the maximum flow objective, is needed as measured at The Dalles Dam on the lower Columbia River. Flood damage begins to occur when flows at The Dalles reach about 450,000 cubic feet per second (currently the river is managed to cap maximum flows at about this level); serious damage occurs at and above 600,000 cubic feet per second. The lower the flow target at The Dalles, the deeper upstream reservoirs will be drafted during the year, with accompanying impacts to other water uses such as recreation and irrigation.    
  • Without the treaty, in order to demonstrate the required “effective use” of U.S. storage before calling upon Canadian storage, the U.S. projects would have to draft deeper more often during called-upon years than is required with the current flood-control operations. These deeper drafts would mean that in the called-upon years some U.S. reservoirs would fail to meet refill requirements.
  • Canadian reservoirs gained some degree of operating flexibility with or without the Treaty.

Following the Phase 1 studies, the U.S. entities conducted a separate series of studies, collected in what is called the Supplemental Report, in which they overlaid the current river-operating requirements – flows and spill at dams required by the Endangered Species Act to protect listed salmon and steelhead – on the Phase 1 studies. These studies give a more accurate picture of how river operations could change if the Treaty is terminated or modified.

Some results of the supplemental studies include:

  • If the Treaty continues, outflows from Arrow and Duncan reservoirs would be lower in January than the corresponding Phase 1 scenarios because water for downstream salmon and steelhead flows (flow-augmentation) is stored during this time. There was one exception:  If the flow target at The Dalles Dam is 450,000 cubic feet per second, flood control limited the capability to store flow-augmentation water.
  • If the Treaty continues, outflows from Arrow and Duncan would be higher in the spring than were shown in the Phase 1 studies, which did not account for flow augmentation. The exception, as above, was if the flow target at The Dalles is 450,000 cubic feet per second.
  • With or without the Treaty, fish operations reduced U.S. hydropower system annual generation by approximately 1,600 average megawatts.
  • With or without the Treaty, the supplemental studies produced less hydropower generation in December through April because of the attempt to keep U.S. reservoirs as high as possible in order to provide flow-augmentation water in the spring and summer.
  • With or without the Treaty, the supplemental studies produced less generation in May through August than the Phase 1 scenarios due to ESA-required spill at dams in the U.S. to aid fish migration.
  • In the Phase 1 studies, the monthly shape of system generation is dramatically different between the Treaty Continues (A and C) and Treaty is Terminated (B2) scenarios. The addition of the fish operations greatly reduces these differences in generation shape.
  • The ability to meet ESA-required spring flow objectives at McNary Dam was largely driven by the maximum flow objective at The Dalles Dam, not by continuing or terminating the Treaty.
  • For the middle 30 (out of 70) volume runoff years, terminating the Treaty caused spring flows at McNary Dam to increase slightly (3 to 13 thousand feet per second) and summer flows to decrease (12 to 14 thousand feet per second). For the lowest 20 volume runoff years, terminating the Treaty caused spring flows to increase slightly (6 thousand feet peer second) and summer flows to decrease (21 to 22 thousand feet per second).
  • In general, none of the scenarios had much of an impact on the flows at Lower Granite Dam on the Snake River in either the spring or summer.

Through the Phase 1 and Supplemental Studies, the U.S. Army Corps of Engineers has been thinking about how flood-risk management might change in the future, whether the Treaty is terminated or continues. The Corps has initiated a comprehensive Flood Risk Management (FRM) study. Here are the key questions the Corps is considering:

  • What is the residual flood risk in the Columbia River Basin under the current Columbia River Flood Control Operating Plan?
  • Can we adequately manage flood risk through a “called upon” system for Canadian storage?
  • What are the implications of climate change for basin hydrology and flood risk between now and 2024?  After 2024?
  • What is the economic value of Canadian flood control storage to the U.S.?
  • What are the potential non-economic (especially environmental) consequences for other river uses and benefits associated with flood-risk management alternatives?

In 2010, following completion of the initial studies and anticipating further studies on the way to formulating recommendations about the future of the Treaty, the U.S. and Canadian entities issued a document that, among other things defined their unique perspectives. Here are some of the points that define the U.S. Entity’s perspective:

  • The lack of coordinated hydropower operations on an international river system such as the Columbia could result in significant uncertainty for downstream U.S. power, flood-control, fisheries, and other non-power river uses and operations.
  • Expectations are that called-upon flood control in Canada will be needed to protect U.S. communities after 2024, but how much is needed, how it will be implemented, and how it will be paid for are still uncertain and will need to be evaluated in future work.
  • U.S. reservoirs in the Northwest may have to be operated much differently for flood control after 2024, and this could have significant implications for interests around those reservoirs.
  • Without the Treaty, the U.S. retains about 300-500 average megawatts of hydropower energy annually, and 1,300-1,500 megawatts of hydropower generating capacity.
  • Many of the current U.S. operations, for example, those required by Biological Opinions under the Endangered Species Act, are not considered when determining Entitlement return to Canada.
  • Consistent with its responsibility for implementing the Treaty, the U.S. Entity is conducting the CRT 2014/2024 Review with input from and coordination with other federal agencies, states, tribes, and stakeholders.
  • Continuation of the Treaty may be managed by the U.S. Entity and Northwest interests, but any amendment or termination must be decided by the U.S. State Department and the President, and any amendments must be approved by the U.S. Senate  (with an equivalent process in Canada).
  • Coordination and communication on CRT 2014/2024 Review activities continue with the Department of State. Expectations are that the U.S. Entity will provide a recommendation on the Treaty future to the Department of State by late 2013.

And here are some of the points that define the Canadian Entity’s perspective:

  • The Canadian Entitlement delivery is the primary benefit of the Treaty to Canada. The value of Canadian Entitlement to British Columbia is approximately $200 to $300 million annually.
  • If the Treaty is terminated, operations of Mica and Duncan dams may not change substantially, and Arrow Reservoir may be kept higher for power generation with more constant outflows throughout the year. Arrow operation is the most critical for U.S. flood control, and therefore is most impacted by called-upon operations.
  • Called-upon flood control assumptions in the Phase 1 study were too conservative and overestimated the frequency and volume of storage required. Other U.S. reservoirs need to be examined to evaluate their “effective use” contribution to U.S. flood control.
  • The entities have different opinions regarding the flood control rights after 2024 (for example, whether the maximum flow objective should be 450,000 or 600,000 cubic feet per second at The Dalles Dam.

Next steps

According to the U.S. and Canadian entities, there was much work to be done to follow up on the Phase 1 and supplemental studies. For example, while the purpose of the Phase 1 studies was to look at post-2024 conditions with and without the current Treaty from the perspective of the two purposes of the Treaty, power and flood control, those are not the only uses of the river and dams today. Additional collaborative work was needed to understand the implications for the Treaty on alternative operations to meet ESA-required flow objectives at the U.S. dams for salmon and steelhead. Other concerns, such as ecosystem health, water supply and quality, potential climate-change impacts, cultural resources, recreation, navigation, and irrigation needed to be considered as well.

In 2011, 2012, and 2013, the U.S. and Canadian entities conducted studies, addressed the various issues, and formulated draft and then final recommendations to submit to their respective national governments.

In December 2013, the U.S. Entity released its Regional Recommendation. The recommendation was developed by the Entity with input from representatives of sovereign governments (organized as the Sovereign Review Team comprising representatives of the states of Washington, Oregon, Idaho and Montana, 10 federal agencies, and 15 tribes), and regional stakeholders through a process that involved extensive meetings and consultations throughout the Northwest. The U.S. Entity took the position that its recommendation seeks to formalize, provide certainty, and build on the many ecosystem actions already undertaken through annual or seasonal mutual agreements between the countries, while also providing a net increase in U.S. power benefits based on the actual value of coordinated operations with Canada, preserving an acceptable level of flood risk to the people of the Columbia River Basin, and continuing to recognize and implement the other authorized purposes in the basin. In the recommendation, the term “modernization” of the Treaty refers to the construct of a post-2024 arrangement. According to the Entity, this construct could include amendments or revisions to the existing Treaty, diplomatic notes or protocols, or other means resulting in a "modernized" Treaty.

The following nine key principles underlie the U.S. Entity’s recommendation:

  1. Treaty provisions should enable the greatest possible shared benefits in the United States and Canada from the coordinated operation of Treaty reservoirs for ecosystem, hydropower, and flood risk management, as well as water supply, recreation, navigation, and other pertinent benefits and uses, as compared to no longer coordinating Treaty storage operations.
  2. The health of the Columbia River ecosystem should be a shared benefit and cost of the United States and Canada.
  3. The minimum duration of the Treaty post-2024 should be long enough to allow each country to rely on the Treaty’s planned operations and benefits for purposes of managing their long-range budgets, resource plans, and investments, but adaptable enough to allow responses to new information and changing conditions.
  4. All operations of the Treaty should be based on the best available science, and, to the extent practicable, measurable outcomes.
  5. U.S. federal reservoirs/projects will continue to meet authorized uses consistent with applicable legislation, Indian treaties and tribal rights, the U.S. government’s trust responsibility to the tribes, and other U. S. laws such as the Clean Water Act and the Endangered Species Act. Non-federal U.S. projects will continue to meet their responsibilities pursuant to their Federal Energy Regulatory Commission licenses.
  6. The United States and Canada should pursue a more coordinated use of Treaty and Canadian non-Treaty storage under the Treaty to increase the flexibility to, and benefits of, meeting ecosystem-based function, power, flood risk management, and other authorized water management purposes in both countries.
  7. The region anticipates impacts from climate change to all of the elements described in the recommendations. The strategy for adapting the Treaty to future changes in climate should be resilient, adaptable, flexible, and timely as conditions warrant.
  8. It is recognized that modifications to the Treaty could result in new benefits and/or costs to both Canada and the United States. U.S. interests should ensure that costs associated with any Treaty operation are aligned with the appropriate party.
  9. Implementation of ecosystem-based functions in the Treaty should be compatible with rebalancing the entitlement and reducing U.S. power costs.

In March 2014, the Province of British Columbia released its recommendation, based on a draft produced by the Canadian Entity in late 2013.  The Province asserted that the Treaty should continue but should be improved within the existing Treaty framework consistent with the following 14 principles:

  1. The primary objective of the Treaty should be to maximize benefits to both countries through the coordination of planning and operations.
  2. The ongoing impacts to the Canadian Columbia Basin to meet Treaty requirements should be acknowledged and compensated for. The level of benefits to the Province, which is currently solely in the form of the Canadian Entitlement, does not account for the full range of benefits in the United States (U.S.) or the impacts in British Columbia.
  3. All downstream U.S. benefits, such as flood risk management, hydropower, ecosystems, water supply (including municipal, industrial and agricultural uses), recreation, navigation and any other relevant benefits, including associated risk reduction arising from coordinated operations compared to alternatives available to each country, should be accounted for and such value created should be shared equitably between the two countries.
  4. Treaty provisions post-2024 should be fixed for a sufficient duration to provide planning and operational certainty while allowing for adaptive mechanisms to address significant changes to key components and interests.
  5. Implementation of post-2024 flood control obligations will be consistent with the Treaty requirements that a called-upon flood control request can only be made when forecasts of potential floods indicate there is a reasonable risk of exceeding 600,000 cubic feet per second at The Dalles, Oregon, the U.S. must make effective use of all related storage in the U.S. before seeking additional help from British Columbia, and the U.S. must pay Canada compensation due as result of a called-upon operation.
  6. To supplement called-upon flood control, a coordinated flood-risk management approach should maximize the benefits and mitigate impacts and risks to multiple U.S. interests as compared to a called-upon flood control regime post 2024 that includes effective use of U.S. reservoirs.
  7. Ecosystem values are currently, and will continue to be, an important consideration in the planning and implementation of the Treaty.
  8. The Province will explore ecosystem-based improvements recognizing that there are a number of available mechanisms inside and outside the Treaty.
  9. Current and future operating conditions of Canadian Columbia Basin dams and reservoirs are subject to provincial and federal licensing including Water Use Plans, where they exist, and consideration of aboriginal rights under the Canadian constitution.
  10. The Province will seek improved coordination on Libby Dam and Koocanusa Reservoir operations.
  11. Salmon migration into the Columbia River in Canada was eliminated by the Grand Coulee Dam in 1938 (26 years prior to Treaty ratification), and is currently not a Treaty issue. British Columbia’s perspective is that the management of anadromous salmon populations is the responsibility of the Government of Canada and that restoration of fish passage and habitat, if feasible, should be the responsibility of each country regarding their respective infrastructure.
  12. Adaptation to climate change should be incorporated in Treaty planning and implementation.
  13. The Canadian entities (Province of British Columbia, and BC Hydro) will continue to consult with First Nations on a government-to-government basis and engage with Basin communities throughout any negotiation process.
  14. Canadian Columbia River Basin issues not related to the Treaty will be addressed through other government programs and initiatives.

The next step in both countries is for the U.S. State Department and Global Affairs Canada to review the recommendations.  The first opportunity for either country to announce its intention regarding the future of the Treaty was September 16, 2014. Since then there has been little activity, other than staff work by the State Department and Global Affairs Canada. Since then there was little activity, other than staff work by the State Department and Global Affairs Canada.

In March 2015, U.S. Senator Patty Murray (D-Washington) wrote to President Obama urging that the future of the treaty receive high priority. In response, Julia Frifield, assistant secretary for legislative affairs at the State Department replied in a May 20, 2015 letter that “the Administration recognizes the significant economic and cultural role the Columbia River plays in the lives of your constituents” and that “the future of the treaty is a priority.” She added, “internal deliberations are gaining momentum.”

Frifield also wrote that, consistent with the U.S. Entity’s recommendation, “we have decided to include flood risk mitigation, ecosystem-based function, and hydropower generation in the draft U.S. negotiating position.” She said the U.S. hoped to approach Canada soon to begin “discussions on modernization of the treaty.”

By early 2016, there had been no public notice that those discussions had begun, but other Northwest members of Congress took advantage of the visit between President Obama and the newly elected Prime Minister of Canada, Justin Trudeau, to raise the treaty future again.

On March 10, 2016, Senator Maria Cantwell (D-Washington) issued a press release announcing that she had sent a letter to Trudeau “urging modernization of the treaty.” In her news release, Cantwell wrote, “a modernized Columbia River Treaty would provide opportunities for the United States and Canada to address current climate challenges and its [sic] impact on water resources.” adding, “I believe we must find a mutually beneficial path forward to modernize the treaty in a way that balances flood control, ecosystem-based function, and hydropower generation.”

The following week, on March 18, U.S. Reps. Cathy McMorris-Rodgers (R-Washington) and Peter DeFazio (D-Oregon) issued a joint press release announcing that they “met with Canadian Members of Parliament this week to discuss important issues along the United States northwest border with Canada -- border security and access, water and energy policy, and the sale and transportation of goods.” Included in these conversations, according to the release, was “the importance of the Columbia River Treaty … [which] plays an indispensable role in the livelihoods of those in the Pacific Northwest.” They said they wrote to President Obama asking him to raise the treaty in his talks with Trudeau. They also said the downstream benefit paid annually by the Unites States to Canada under terms of the existing treaty needs to be “rebalanced.” If it is not rebalanced by 2024, they wrote, “Pacific Northwest ratepayers will lose roughly $1 million every 2-3 days or about $150 million a year.” They added that the State Department “needs to conclude its review process and initiate negotiations with Canada.”

Finally, on May 22, 2018, the two governments issued simultaneous news releases announcing negotiations would get under way on May 29 in Washington, D.C. These news releases are linked in the sidebar to this article.

In a sense, though, the public process to consider the future of the Treaty unofficially got under way in Spokane in April 2018 at a conference hosted by the Lake Roosevelt Forum, an association of governments, interest groups, state agencies, and citizens who work and live on Lake Roosevelt, the reservoir behind Grand Coulee Dam.

The April conference featured a speech by a U.S. State Department official, a panel discussion among Treaty interests, and a town hall meeting presided over by the U.S. negotiating team.

The team includes the chief U.S. State Department negotiator, Jill Smail, and representatives of the Bonneville Power Administration, Bureau of Reclamation, Army Corps of Engineers, and NOAA Fisheries.

Francisco “Paco” Palmieri, acting assistant secretary for the Bureau of Western Hemisphere Affairs in the State Department, whose responsibilities include the 1964 Treaty, promised to “engage with the region” as negotiations get under way and to conduct periodic public meetings during the process.

“The brilliance of the Treaty is to determine how we share resources for mutual benefits,” he said. “The Treaty is seen around the world as a model of transboundary cooperation, and we hope it will continue as a model for many, many years to come.” A video of his speech is posted here.

At the evening town hall meeting, attended by about 125 people, Smail said the team would represent the United States and intended to pursue the regional recommendation as developed by the U.S. Entity and regional participants in 2013. The U.S. entity for Treaty implementation consists of the Bonneville Power Administration and the Corps of Engineers. While tribal governments were included in the development of the regional recommendation in 2013, they were not consulted about the original Treaty in the 1960s.

The United States’ regional recommendation calls for continuing the primary purposes of the Treaty, hydropower and flood control, but also recognizes “… there is an opportunity for inclusion of certain additional ecosystem operations to expand, enhance, and complement … existing ecosystem investments as part of the post-2024 Treaty.” The B.C. Decision states, “Ecosystem values are currently, and will continue to be, an important consideration in the planning and implementation of the Treaty,” and “The Province will explore ecosystem-based improvements recognizing that there are a number of available mechanisms inside and outside the Treaty.”

While the regional recommendations of the two countries recognize but do not define “ecosystem benefits,” a coalition of Columbia River Basin tribes has defined the term (see page 7 of the hyperlinked document), in a June 2013 statement about the future of the Treaty. In the tribes’ definition, ecosystem function includes a number of river operations to benefit fish and wildlife including, for example, increased spring and summer flows, higher and more stable storage reservoir levels, lower summer water temperatures, and reconnected floodplain habitats.

Ecosystem function and the makeup of the United States’ negotiating team dominated public comments at the Spokane Town Hall meeting in April. Many speakers including representatives of tribes and environmental groups supported the inclusion of ecosystem considerations in a “modernized Treaty,” as Smail called it, and these same groups decried the lack of tribal representation on the negotiating team. Smail said the team would represent the United States and intended to pursue the regional recommendation as developed by the U.S. Entity and regional participants, including tribes, in 2013. Tribal governments, she said, would not be part of the negotiating team.

Earlier the same day, at the Lake Roosevelt Forum conference where Palmieri spoke, eight invited panelists representing U.S. and Canadian tribes and economic, community, and environmental interests from both sides of the border noted the many things they hope to see authorized or delivered by a modernized Treaty, from flood control to hydropower to irrigation to navigation and improved ecosystem conditions for fish and wildlife. Panelist Tom Karier, eastern Washington member of the Northwest Power And Conservation Council, represented Washington Governor Jay Inslee in advising the U.S. Entity as it developed the 2013 regional recommendation.

“We’ve been working on the Treaty for the last eight years,” Karier said. “The original Treaty was simple – build dams, share benefits; but there were important omissions – the tribes, ecosystem function,” he said. “What is the objective of a new Treaty? The issue today is not whether to build dams. The key question for the next Treaty is how are those dams operated? If Canada operates them in way that is ideal for the U.S., we don’t need a Treaty.

“The real objective is how do we identify a different set of operations that would benefit the U.S. and also Canada? We need to protect human health and safety; for the most part we need some storage upriver. We need certain flows to help salmon survive. We can work together to optimize power operations, and the power system can help mitigate climate-change impacts. The right answer is in the nuances.”

The first negotiating session of the treaty review effort took place in Washington, D.C. on May 29 and 30, 2018.  Palmieri welcomed the U.S. and Canadian negotiating teams, thanking them for "more than 50 years of remarkable coordination."  The press and public were excluded from the closed-door session, and afterward officials would not discuss specific topics, but U.S. officials reiterated their commitment to use the 2013 Regional Recommendation as the basis of their negotiating posiiltions.

In written remarks before the Washington, D.C. session, Palmieri said, "Good treaties make good neighbors. The United States and Canada have a long, positive history of engagement on the Columbia River." He said he expected that cooperative spirit to continue in the negotiations.  In a news release after the sessions, the State Department  said Palmieri lauded the long history of "excellent transboundary collaboration in the Columbia River Basin."

A second negotiating session was conducted in August in Nelson, British Columbia, and a third in Portland in October 2018.  A fourth is scheduled December 12-13 in Vancouver, B.C. A second public meeting was conducted in Portland in September and another is planned in January 2019; the site and date have not been announced, but it likely will be in British Columbia.

At the Portland public meeting, the remote potential but real concern for flooding low-lying areas around Portland if the treaty is not revised dominated the remarks. Coincidentally, 2018 is the 70th anniversary of the Vanport Flood, which wiped out the community along the Columbia River north of Portland, leaving 15 people dead and 18,000 homeless. The 1948 flood was a key event that prompted the initial talks between the United States and Canada about a flood-control treaty for the Columbia River, which begins in British Columbia.

Portland Mayor Ted Wheeler and representatives of the ports of Portland and Vancouver, and Portland-area diking districts, predicted that flood risk would increase for billions of dollars in commerce and property if the treaty expired under its existing language, which would change flood control rules. Unless the treaty is changed, at the end of its 60-year life in 2024, “assured” flood control now provided by Canada would change to a regime in which the United States would “call upon” Canada to hold water in reservoirs in British Columbia to control flooding downriver, and pay for it. Under the current treaty, the United States paid for 60 years of flood control when the treaty was ratified by both countries.

Wheeler said the city recognizes the “complexity and sensitivity of the process needed to balance the needs of our region in order to modernize the treaty,” and that flood-risk management, regional economic benefits provided by the treaty, comprehensive ecosystem management of river flows, salmon and lamprey recovery, and tribal sovereignty and treaty rights are key issues important to the city that should be addressed in the negotiations. He also said, as did several other speakers, that tribes should be included on the negotiating team. No tribal representatives spoke at the hearing, although several were in the audience; tribal representatives met privately with the U.S. team earlier in the day.

Bill Bradbury and Jim McKenna, jointly representing Oregon Governor Kate Brown, said 40 percent of the power Oregonians consume comes from the Columbia River and that a new or revised treaty “must provide Oregon access to affordable, reliable, sustainable electric power” while also assuring continued control of potential floods, which could wreak havoc with “national assets” including the Portland airport and Columbia River ports, and also vast areas of low-lying neighborhoods. The treaty also must continue to provide a mechanism for irrigation water withdrawals without affecting ecosystem benefits, McKenna said.

“The Columbia River Treaty modernization must not result in increased flood risk for the lower Columbia,” Bradbury said. If the treaty were left to run its course, “how would called-upon payments to Canada be calculated, and who would pay for it?’ he asked.

Lead negotiator Smail, who presided at the Sept. 6 Portland meeting as she had in Spokane in April, said the U.S. and Canadian teams “have been quite busy” since the April public meeting. She noted the two negotiating sessions and the April public meeting. But as she said at the April meeting and reiterated at the Portland meeting, tribes will not be part of the negotiating team. Canadian first nations are not included on the Canadian negotiating team, either.

Reading from a prepared statement, Smail said, “we value the Tribes’ expertise and experience and are working with them to develop a mechanism for meaningful engagement throughout the negotiations.” Tribes were involved in developing the U.S. regional recommendation but are not represented on the negotiating team.

“This is a very exciting time to be working on the Treaty,” Smail continued. “People here in the Northwest have anticipated and planned for this for many years. At the Department of State, we are eager to move forward to help define how Americans and Canadians – including Tribes in the United States and First Nations in Canada – will continue to mutually benefit from the Treaty.” Perhaps in a nod to the current tensions with Canada over the North American Free Trade Agreement, she said the treaty “is an extremely important agreement with one of our best allies and partners in the hemisphere. We deeply value our unique and essential relationship with Canada.”

One issue important to American tribes and Canadian first nations, reintroduction of salmon to the Columbia River Basin above Grand Coulee Dam, which has blocked their passage since the late 1930s, was raised by several people, prompting responses from Lorri Gray, Northwest regional director of the Bureau of Reclamation, which operates the dam, and Smail.

“The topic has been put on the table,” Gray said. “It’s a technically difficult question, trying to figure out what that looks like, but we are listening. We understand the interest, and we also understand the technical difficulties.”

Smail said fish reintroduction “will be discussed with Canada at some point in the negotiations,” adding, “we have agreed to that.”